ITAC Assessment: WV0685
ITAC logo
ITAC Assessment: WV0685
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Metal
NAICS 332313: Plate Work Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 80,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 5,775
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,973 755,318
kWh
Electricity Demand $58,186 3,497
kW-mo/yr
Electricity Fees $3,011 -
Natural Gas $19,255 1,735
MMBtu
TOTAL YEARLY COSTS $122,425
RECOMMENDED SAVINGS* $29,694 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,445 $16,580 $6,173
103,567
kWh
$8,272
-
kW-mo/yr
02 2.7135: Install occupancy sensors $7,381 $3,621 $4,502
75,530
kWh
$2,879
-
kW-mo/yr
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,411 $9,050 - $3,411
-
kW-mo/yr
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,123 $513 $1,341
22,499
kWh
$782
-
kW-mo/yr
05 2.7241: Install outside air damper / economizer on hvac unit $1,728 $8,100 $796
13,356
kWh
$932
-
kW-mo/yr
06 2.4239: Eliminate or reduce compressed air usage $366 $435 $233
3,905
kWh
$133
-
kW-mo/yr
07 2.4231: Reduce the pressure of compressed air to the minimum required $240 $210 $157
2,633
kWh
$83
-
kW-mo/yr
TOTAL RECOMMENDED $29,694 $38,509 $13,202
221,490
kWh
$16,492
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs