| Assessment Year | 2025 |
|---|---|
| Principal Product | Metal |
| NAICS | 332313: Plate Work Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
80,000
ft2
|
| Annual Production | 10,000
units
|
| Production Hrs. Annual | 5,775
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $41,973 | 755,318 |
kWh
|
$0.056 |
| Electricity Demand | $58,186 | 3,497 |
kW-mo/yr
|
$16.64 |
| Electricity Fees | $3,011 | - |
|
- |
| Natural Gas | $19,255 | 1,735 |
MMBtu
|
$11.10 |
| TOTAL YEARLY COSTS | $122,425 | |||
| RECOMMENDED SAVINGS* | $29,694 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,445 | $16,580 |
$6,173
103,567
kWh
|
$8,272
-
kW-mo/yr
|
|
| 02 | 2.7135: Install occupancy sensors | $7,381 | $3,621 |
$4,502
75,530
kWh
|
$2,879
-
kW-mo/yr
|
|
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,411 | $9,050 | - |
$3,411
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,123 | $513 |
$1,341
22,499
kWh
|
$782
-
kW-mo/yr
|
|
| 05 | 2.7241: Install outside air damper / economizer on hvac unit | $1,728 | $8,100 |
$796
13,356
kWh
|
$932
-
kW-mo/yr
|
|
| 06 | 2.4239: Eliminate or reduce compressed air usage | $366 | $435 |
$233
3,905
kWh
|
$133
-
kW-mo/yr
|
|
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $240 | $210 |
$157
2,633
kWh
|
$83
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $29,694 | $38,509 |
$13,202
221,490
kWh
|
$16,492
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs