17
matching recommendations
$
$
ARC | 2+ Digits Required | |
NAICS | Secondary smelting, refining, and alloying of nonferrous metal (except copper and aluminum) | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
MZ0107 #12 Y:2012 | 12 | 2012 | Use photocell controls | $265 | $320 | |
MZ0107 #11 Y:2012 | 11 | 2012 | Repair furnaces and oven doors so that they seal efficiently | $845 | $1,115 | |
MZ0107 #10 Y:2012 | 10 | 2012 | Use optimum thickness insulation | $1,288 | $1,499 | |
MZ0107 #09 Y:2012 | 09 | 2012 | Install compressor air intakes in coolest locations | $1,541 | $1,810 | |
MZ0107 #08 Y:2012 | 08 | 2012 | Reduce the pressure of compressed air to the minimum required | $2,356 | $710 | |
MZ0107 #07 Y:2012 | 07 | 2012 | Repair furnaces and oven doors so that they seal efficiently | $2,484 | $1,261 | |
MZ0107 #06 Y:2012 | 06 | 2012 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,600 | $1,745 | |
MZ0107 #05 Y:2012 | 05 | 2012 | Install occupancy sensors | $4,907 | $3,080 | |
MZ0107 #04 Y:2012 | 04 | 2012 | Use optimum thickness insulation | $6,130 | $1,825 | |
MZ0107 #03 Y:2012 | 03 | 2012 | Re-size charging openings or add a movable door on equipment | $12,972 | $3,240 | |
MZ0107 #02 Y:2012 | 02 | 2012 | Reduce combustion air flow to optimum | $43,709 | $1,000 | |
MZ0107 #01 Y:2012 | 01 | 2012 | Use waste heat from hot flue gases to preheat | $76,156 | $80,528 | |
MZ0007 #05 Y:2007 | 05 | 2007 | Install occupancy sensors | $5,535 | $3,250 | |
MZ0007 #04 Y:2007 | 04 | 2007 | Disconnect ballasts | $27,567 | $1,310 | |
MZ0007 #03 Y:2007 | 03 | 2007 | Utilize controls to operate equipment only when needed | $533 | - | |
MZ0007 #02 Y:2007 | 02 | 2007 | Preheat combustion air with waste heat | $10,000 | $20,000 | |
MZ0007 #01 Y:2007 | 01 | 2007 | Cover open tanks | $2,560 | - |