Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

36

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Iron and steel pipe and tube manufacturing from purchased steel
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
WV0331 #11 Y:2005 Chill water to the highest temperature possible $438 $30
WV0331 #10 Y:2005 Utilize a less expensive cooling method $566 $1,370
WV0331 #09 Y:2005 Eliminate leaks in inert gas and compressed air lines/ valves $686 $440
WV0331 #08 Y:2005 Reduce the pressure of compressed air to the minimum required $778 $1,460
WV0331 #07 Y:2005 Analyze flue gas for proper air/fuel ratio $2,352 $1,000
WV0331 #06 Y:2005 Eliminate or reduce compressed air usage $2,523 $320
WV0331 #05 Y:2005 Eliminate or reduce compressed air usage $2,906 $1,560
WV0331 #04 Y:2005 Insulate bare equipment $3,957 $2,264
WV0331 #03 Y:2005 Reduce ventilation air $9,874 $3,940
WV0331 #02 Y:2005 Utilize higher efficiency lamps and/or ballasts $14,865 $22,825
WV0331 #01 Y:2005 Use cooling tower or economizer to replace chiller cooling $15,465 $18,600
WI0499 #07 Y:2005 Install spectral reflectors / delamp $344 -
WI0499 #06 Y:2005 Install compressor air intakes in coolest locations $967 $1,280
WI0499 #05 Y:2005 Use or replace with energy efficient substitutes $4,285 $300
WI0499 #04 Y:2005 Utilize higher efficiency lamps and/or ballasts $6,192 $22,500
WI0499 #03 Y:2005 Install equipment (eg compactor) to reduce disposal costs $9,400 -
WI0499 #02 Y:2005 Install timers and/or thermostats $9,925 $600
WI0499 #01 Y:2005 Modify workload $42,000 $3,600
UU0087 #05 Y:2005 Optimize plant power factor $470 $2,900
UU0087 #04 Y:2005 Install compressor air intakes in coolest locations $2,680 $240