| Assessment Year | 2005 |
|---|---|
| Principal Product | Fabrication |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
| Sales Range | $50 M to 100M |
| # of Employees | 70 |
| Plant Area |
60,000
ft2
|
| Annual Production | 2,500,000
lb
|
| Production Hrs. Annual | 2,100
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $28,831 | 721,572 |
kWh
|
$0.040 |
| Electricity Demand | $25,098 | 2,892 |
kW-mo/yr
|
$8.68 |
| Electricity Fees | $12,122 | - |
|
- |
| Natural Gas | $62,682 | 6,502 |
MMBtu
|
$9.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,113 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $63,713 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.426: Modify workload | $42,000 | $3,600 | - | - | - | - | $42,000 | - | |
| 02 | 2.7261: Install timers and/or thermostats | $9,925 | $600 | - | - |
$9,925
-
MMBtu
|
- | - | - | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,400 | - | - | - | - | - | - | $9,400 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,192 | $22,500 |
$2,765
65,841
kWh
|
$3,427
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4322: Use or replace with energy efficient substitutes | $4,285 | $300 | - | - | - |
$85
-
MMBtu
|
$4,200 | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $967 | $1,280 |
$348
8,272
kWh
|
$619
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 2.7144: Install spectral reflectors / delamp | $344 | - |
$153
3,654
kWh
|
$191
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $73,113 | $28,280 |
$3,266
77,767
kWh
|
$4,237
-
kW-mo/yr
|
$9,925
-
MMBtu
|
$85
-
MMBtu
|
$46,200 | $9,400 | ||
| TOTAL IMPLEMENTED | $63,713 | $28,280 |
$3,266
77,767
kWh
|
$4,237
-
kW-mo/yr
|
$9,925
-
MMBtu
|
$85
-
MMBtu
|
$46,200 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs