ITAC Assessment: WV0331
ITAC logo
ITAC Assessment: WV0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Hose and Tubing
NAICS 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 160,000
ft2
Annual Production 48,000
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $98,110 5,452,982
kWh
Electricity Demand $174,387 12,155
kW-mo/yr
Electricity Fees $47,664 -
Natural Gas $120,571 15,614
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,410 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,067

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2614: Use cooling tower or economizer to replace chiller cooling $15,465 $18,600 $7,493
280,401
kWh
$7,972
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,865 $22,825 $7,204
269,577
kWh
$7,661
-
kW-mo/yr
- -
03 2.7314: Reduce ventilation air $9,874 $3,940 - - $9,874
-
MMBtu
-
04 2.2511: Insulate bare equipment $3,957 $2,264 $1,916
71,785
kWh
$2,041
-
kW-mo/yr
- -
05 2.4239: Eliminate or reduce compressed air usage $2,906 $1,560 $1,409
52,647
kWh
$1,497
-
kW-mo/yr
- -
06 2.4239: Eliminate or reduce compressed air usage $2,523 $320 $1,221
45,776
kWh
$1,302
-
kW-mo/yr
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $2,352 $1,000 - - $2,532
-
MMBtu
$(-180.0)
08 2.4231: Reduce the pressure of compressed air to the minimum required $778 $1,460 $377
14,102
kWh
$401
-
kW-mo/yr
- -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $686 $440 $392
14,710
kWh
$414
-
kW-mo/yr
- $(-120.0)
10 2.2628: Utilize a less expensive cooling method $566 $1,370 $274
10,255
kWh
$292
-
kW-mo/yr
- -
11 2.2625: Chill water to the highest temperature possible $438 $30 $212
7,957
kWh
$226
-
kW-mo/yr
- -
TOTAL RECOMMENDED $54,410 $53,809 $20,498
767,210
kWh
$21,806
-
kW-mo/yr
$12,406
-
MMBtu
$(-300.0)
TOTAL IMPLEMENTED $28,067 $29,869 $12,519
468,597
kWh
$13,316
-
kW-mo/yr
$2,532
-
MMBtu
$(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs