ITAC Assessment: UU0087
ITAC logo
ITAC Assessment: UU0087
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Pipe
NAICS 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3317: Steel Pipe and Tubes
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 75,900
ft2
Annual Production 8,000
ton
Production Hrs. Annual 2,350
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,590 1,138,905
kWh
Electricity Demand $55,623 6,159
kW-mo/yr
Natural Gas $132,072 21,053
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $102,630 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 4.511: Expand operations into unused space $84,030 $200,000 - - $84,030
-
MMBtu
02 2.3191: Use demand controller or load shedder $9,270 - - $9,270
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,180 $3,040 $1,790
64,080
kWh
$4,390
-
kW-mo/yr
-
04 2.4221: Install compressor air intakes in coolest locations $2,680 $240 $840
30,170
kWh
$1,840
-
kW-mo/yr
-
05 2.3212: Optimize plant power factor $470 $2,900 - $470
-
kW-mo/yr
-
TOTAL RECOMMENDED $102,630 $206,180 $2,630
94,250
kWh
$15,970
-
kW-mo/yr
$84,030
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs