| Assessment Year | 2005 |
|---|---|
| Principal Product | Pipe |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 3317: Steel Pipe and Tubes |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
75,900
ft2
|
| Annual Production | 8,000
ton
|
| Production Hrs. Annual | 2,350
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,590 | 1,138,905 |
kWh
|
$0.028 |
| Electricity Demand | $55,623 | 6,159 |
kW-mo/yr
|
$9.03 |
| Natural Gas | $132,072 | 21,053 |
MMBtu
|
$6.27 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $102,630 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 4.511: Expand operations into unused space | $84,030 | $200,000 | - | - |
$84,030
-
MMBtu
|
|
| 02 | 2.3191: Use demand controller or load shedder | $9,270 | - | - |
$9,270
-
kW-mo/yr
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,180 | $3,040 |
$1,790
64,080
kWh
|
$4,390
-
kW-mo/yr
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $2,680 | $240 |
$840
30,170
kWh
|
$1,840
-
kW-mo/yr
|
- | |
| 05 | 2.3212: Optimize plant power factor | $470 | $2,900 | - |
$470
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $102,630 | $206,180 |
$2,630
94,250
kWh
|
$15,970
-
kW-mo/yr
|
$84,030
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs