503
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| LE0293 #03 Y:2009 | 03 | 2009 | Use adjustable frequency drive or multiple speed motors on existing system | $4,105 | $2,932 | |
| LE0293 #02 Y:2009 | 02 | 2009 | Eliminate leaks in inert gas and compressed air lines/ valves | $9,797 | $1,800 | |
| LE0293 #01 Y:2009 | 01 | 2009 | Use batch firing with kiln "furniture" specifically designed | $25,144 | $15,000 | |
| NC0393 #05 Y:2009 | 05 | 2009 | Utilize higher efficiency lamps and/or ballasts | $967 | $2,795 | |
| NC0393 #04 Y:2009 | 04 | 2009 | Eliminate leaks in inert gas and compressed air lines/ valves | $256 | $100 | |
| NC0393 #03 Y:2009 | 03 | 2009 | Recycle air for heating, ventilation and air conditioning | $6,020 | $2,216 | |
| NC0393 #02 Y:2009 | 02 | 2009 | Reschedule plant operations or reduce load to avoid peaks | $31,650 | $1,000 | |
| NC0393 #01 Y:2009 | 01 | 2009 | Utilize a less expensive cooling method | $32,824 | $74,000 | |
| SF0367 #12 Y:2008 | 12 | 2008 | Use adjustable frequency drive or multiple speed motors on existing system | $5,318 | $11,290 | |
| SF0367 #11 Y:2008 | 11 | 2008 | Utilize controls to operate equipment only when needed | $14,022 | $18,000 | |
| SF0367 #10 Y:2008 | 10 | 2008 | Use adjustable frequency drive or multiple speed motors on existing system | $7,802 | $10,433 | |
| SF0367 #09 Y:2008 | 09 | 2008 | Utilize controls to operate equipment only when needed | $11,030 | $7,537 | |
| SF0367 #08 Y:2008 | 08 | 2008 | Use adjustable frequency drive or multiple speed motors on existing system | $21,234 | $9,745 | |
| SF0367 #07 Y:2008 | 07 | 2008 | Install occupancy sensors | $9,914 | $1,497 | |
| SF0367 #06 Y:2008 | 06 | 2008 | Utilize controls to operate equipment only when needed | $14,633 | $1,078 | |
| SF0367 #05 Y:2008 | 05 | 2008 | Install timers and/or thermostats | $1,679 | $143 | |
| SF0367 #04 Y:2008 | 04 | 2008 | Turn off equipment when not in use | $360 | - | |
| SF0367 #03 Y:2008 | 03 | 2008 | Use optimum size and capacity equipment | $16,340 | $5,460 | |
| SF0367 #02 Y:2008 | 02 | 2008 | Use optimum size and capacity equipment | $121,210 | $720 | |
| SF0367 #01 Y:2008 | 01 | 2008 | Use optimum size and capacity equipment | $169,502 | $10,920 |