ITAC Assessment: SF0367
ITAC logo
ITAC Assessment: SF0367
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Silicon Carbide
NAICS 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing
SIC 3299: Nonmetallic Mineral Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 20
Plant Area 15,000
ft2
Annual Production 1
units
Production Hrs. Annual 8,760
hrs
Location (State) Hawaii

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $997,391 2,868,600
kWh
Electricity Demand $79,493 7,607
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $393,044 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $393,044

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4323: Use optimum size and capacity equipment $169,502 $10,920 $169,502
487,508
kWh
-
02 2.4323: Use optimum size and capacity equipment $121,210 $720 $113,100
325,279
kWh
$8,110
-
kW-mo/yr
03 2.4323: Use optimum size and capacity equipment $16,340 $5,460 $16,340
46,997
kWh
-
04 2.6218: Turn off equipment when not in use $360 - $360
1,043
kWh
-
05 2.7261: Install timers and/or thermostats $1,679 $143 $1,679
4,828
kWh
-
06 2.6231: Utilize controls to operate equipment only when needed $14,633 $1,078 $14,633
42,085
kWh
-
07 2.7135: Install occupancy sensors $9,914 $1,497 $9,242
24,373
kWh
$672
-
kW-mo/yr
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $21,234 $9,745 - $21,234
-
kW-mo/yr
09 2.6231: Utilize controls to operate equipment only when needed $11,030 $7,537 $11,030
31,724
kWh
-
10 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,802 $10,433 $7,394
21,267
kWh
$408
-
kW-mo/yr
11 2.6231: Utilize controls to operate equipment only when needed $14,022 $18,000 $14,022
40,330
kWh
-
12 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $5,318 $11,290 $5,318
15,295
kWh
-
TOTAL RECOMMENDED $393,044 $76,823 $362,620
1,040,729
kWh
$30,424
-
kW-mo/yr
TOTAL IMPLEMENTED $393,044 $76,823 $362,620
1,040,729
kWh
$30,424
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs