Assessment Year | 2008 |
---|---|
Principal Product | Silicon Carbide |
NAICS | 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing |
SIC | 3299: Nonmetallic Mineral Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 20 |
Plant Area |
15,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Hawaii |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $997,391 | 2,868,600 |
kWh
|
$0.35 |
Electricity Demand | $79,493 | 7,607 |
kW-mo/yr
|
$10.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $393,044 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $393,044 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $169,502 | $10,920 |
$169,502
487,508
kWh
|
- | |
02 | 2.4323: Use optimum size and capacity equipment | $121,210 | $720 |
$113,100
325,279
kWh
|
$8,110
-
kW-mo/yr
|
|
03 | 2.4323: Use optimum size and capacity equipment | $16,340 | $5,460 |
$16,340
46,997
kWh
|
- | |
04 | 2.6218: Turn off equipment when not in use | $360 | - |
$360
1,043
kWh
|
- | |
05 | 2.7261: Install timers and/or thermostats | $1,679 | $143 |
$1,679
4,828
kWh
|
- | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $14,633 | $1,078 |
$14,633
42,085
kWh
|
- | |
07 | 2.7135: Install occupancy sensors | $9,914 | $1,497 |
$9,242
24,373
kWh
|
$672
-
kW-mo/yr
|
|
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,234 | $9,745 | - |
$21,234
-
kW-mo/yr
|
|
09 | 2.6231: Utilize controls to operate equipment only when needed | $11,030 | $7,537 |
$11,030
31,724
kWh
|
- | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,802 | $10,433 |
$7,394
21,267
kWh
|
$408
-
kW-mo/yr
|
|
11 | 2.6231: Utilize controls to operate equipment only when needed | $14,022 | $18,000 |
$14,022
40,330
kWh
|
- | |
12 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,318 | $11,290 |
$5,318
15,295
kWh
|
- | |
TOTAL RECOMMENDED | $393,044 | $76,823 |
$362,620
1,040,729
kWh
|
$30,424
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $393,044 | $76,823 |
$362,620
1,040,729
kWh
|
$30,424
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs