ITAC Assessment: LE0293
ITAC logo
ITAC Assessment: LE0293
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Industrial wire brushes
NAICS 327910: Abrasive Product Manufacturing
SIC 3291: Abrasive Products
Sales Range $50
M
to 100
M
# of Employees 362
Plant Area 220,500
ft2
Annual Production 1,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,203 4,688,400
kWh
Electricity Demand $92,154 10,556
kW-mo/yr
Fuel Oil #4 $102,506 3,953
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,876 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,520

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings
01 2.2313: Use batch firing with kiln "furniture" specifically designed $25,144 $15,000 $7,890
167,887
kWh
$2,396
-
kW-mo/yr
$14,858
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,797 $1,800 $7,249
101,744
kWh
$2,548
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,105 $2,932 $2,874
68,331
kWh
$1,231
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $2,864 $700 $2,864
60,937
kWh
- -
05 2.4112: Install soft-start to eliminate nuisance trips $1,697 $27,600 - $1,697
-
kW-mo/yr
-
06 2.4221: Install compressor air intakes in coolest locations $717 $1,675 $528
13,429
kWh
$189
-
kW-mo/yr
-
07 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $356 $2,250 $356
7,575
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $13,196 $58,455 $9,816
184,087
kWh
$3,380
-
kW-mo/yr
-
TOTAL RECOMMENDED $57,876 $110,412 $31,577
603,990
kWh
$11,441
-
kW-mo/yr
$14,858
-
MMBtu
TOTAL IMPLEMENTED $57,520 $108,162 $31,221
596,415
kWh
$11,441
-
kW-mo/yr
$14,858
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs