22
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OK0945 #04 Y:2016 | 04 | 2016 | Insulate bare equipment | $14,580 | $10,000 | |
| OK0945 #03 Y:2016 | 03 | 2016 | Utilize higher efficiency lamps and/or ballasts | $21,559 | $26,380 | |
| OK0945 #02 Y:2016 | 02 | 2016 | Reduce the pressure of compressed air to the minimum required | $2,229 | - | |
| OK0945 #01 Y:2016 | 01 | 2016 | Optimize plant power factor | $23,818 | $29,535 | |
| OK0864 #09 Y:2013 | 09 | 2013 | Use flue gas recuperation to reduce voc | $79,353 | $32,100 | |
| OK0864 #08 Y:2013 | 08 | 2013 | Reduce combustion air flow to optimum | $127,574 | $25,000 | |
| OK0864 #07 Y:2013 | 07 | 2013 | Use adjustable frequency drive or multiple speed motors on existing system | $46,176 | $10,642 | |
| OK0864 #06 Y:2013 | 06 | 2013 | Use adjustable frequency drive or multiple speed motors on existing system | $20,158 | $10,250 | |
| OK0864 #05 Y:2013 | 05 | 2013 | Size electric motors for peak operating efficiency | $8,999 | $27,500 | |
| OK0864 #04 Y:2013 | 04 | 2013 | Upgrade controls on compressors | $5,084 | - | |
| OK0864 #03 Y:2013 | 03 | 2013 | Insulate bare equipment | $2,872 | $1,478 | |
| OK0864 #02 Y:2013 | 02 | 2013 | Use most efficient type of electric motors | $655 | $1,128 | |
| OK0864 #01 Y:2013 | 01 | 2013 | Optimize plant power factor | $33,277 | $58,900 | |
| OK0693 #09 Y:2004 | 09 | 2004 | Install occupancy sensors | $356 | $737 | |
| OK0693 #08 Y:2004 | 08 | 2004 | Install timers and/or thermostats | $772 | $1,140 | |
| OK0693 #07 Y:2004 | 07 | 2004 | Reduce the pressure of compressed air to the minimum required | $992 | $1,025 | |
| OK0693 #06 Y:2004 | 06 | 2004 | Utilize higher efficiency lamps and/or ballasts | $808 | $123 | |
| OK0693 #05 Y:2004 | 05 | 2004 | Utilize higher efficiency lamps and/or ballasts | $5,903 | $31,913 | |
| OK0693 #04 Y:2004 | 04 | 2004 | Use cooling tower water instead of refrigeration | $2,179 | $3,635 | |
| OK0693 #03 Y:2004 | 03 | 2004 | Optimize plant power factor | $7,010 | $10,720 | n/a |