ITAC Assessment: OK0693
ITAC logo
ITAC Assessment: OK0693
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Wet-formed fiberglass material
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 75
Plant Area 72,700
ft2
Annual Production 44,500
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $398,550 13,440,000
kWh
Electricity Demand $87,832 20,178
kW-mo/yr
Electricity Fees $17,465 -
Natural Gas $1,916,769 265,661
MMBtu
Other Gas $49,840 37,798
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $631,952 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,031

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2414: Use waste heat from hot flue gases to preheat $585,281 $30,200 - - - $585,281
-
MMBtu
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $28,651 $88,297 $28,651
964,680
kWh
- - - - -
03 2.3212: Optimize plant power factor $7,010 $10,720 n/a - - $7,010 - - -
04 2.2612: Use cooling tower water instead of refrigeration $2,179 $3,635 $1,170
39,410
kWh
$1,009
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,903 $31,913 $2,773
93,382
kWh
$513
-
kW-mo/yr
- - $243 $2,374
06 2.7142: Utilize higher efficiency lamps and/or ballasts $808 $123 $683
22,995
kWh
$125
-
kW-mo/yr
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $992 $1,025 $838
28,231
kWh
$154
-
kW-mo/yr
- - - -
08 2.7261: Install timers and/or thermostats $772 $1,140 - - - $772
-
MMBtu
- -
09 2.7135: Install occupancy sensors $356 $737 $356
11,981
kWh
- - - - -
TOTAL RECOMMENDED $631,952 $167,790 $34,471
1,160,679
kWh
$1,801
-
kW-mo/yr
$7,010 $586,053
-
MMBtu
$243 $2,374
TOTAL IMPLEMENTED $7,031 $33,790 $3,129
105,363
kWh
$513
-
kW-mo/yr
- $772
-
MMBtu
$243 $2,374
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs