ITAC Assessment: UD0683
ITAC logo
ITAC Assessment: UD0683
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product injection molded plastic parts
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 26
Plant Area 35,000
ft2
Annual Production 7,785,000
pieces
Production Hrs. Annual 4,160
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,900 1,275,680
kWh
Electricity Demand $62,200 5,244
kW-mo/yr
Natural Gas $7,641 1,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,005 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,720

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Increase in Production Savings
01 4.424: Improve space comfort conditioning $30,335 $50,000 - - - $3,085 $27,250
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,720 $11,700 $1,400
40,000
kWh
$1,320
-
kW-mo/yr
- - -
03 2.2511: Insulate bare equipment $2,600 $4,625 $1,730
52,400
kWh
$870
-
kW-mo/yr
- - -
04 2.6241: Reduce temperature of process equipment when on standby $1,225 - $1,225
37,065
kWh
- - - -
05 3.4116: Meter recycled water (to reduce sewer charges) $925 - - - $925
-
Tgal
- -
06 2.7121: Utilize daylight whenever possible in lieu of artificial light $200 - $200
6,000
kWh
- - - -
TOTAL RECOMMENDED $38,005 $66,325 $4,555
135,465
kWh
$2,190
-
kW-mo/yr
$925
-
Tgal
$3,085 $27,250
TOTAL IMPLEMENTED $2,720 $11,700 $1,400
40,000
kWh
$1,320
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs