ITAC Assessment: OK0864
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Fiber Glass, roofing material
NAICS 327993: Mineral Wool Manufacturing
SIC 3172: Personal Leather Goods, Except Women's Handbags and Purses
Sales Range $10
M
to 50
M
# of Employees 72
Plant Area 70,000
ft2
Annual Production 34,000,000
lb
Production Hrs. Annual 8,712
hrs
Location (State) Arkansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $489,587 13,252,800
kWh
Electricity Demand $216,737 25,852
kW-mo/yr
Natural Gas $990,710 243,514
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $324,148 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $150,771

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $33,277 $58,900 - - $33,277 -
02 2.4133: Use most efficient type of electric motors $655 $1,128 $499
13,514
kWh
$156
-
kW-mo/yr
- -
03 2.2511: Insulate bare equipment $2,872 $1,478 - - - $2,872
-
MMBtu
04 2.4224: Upgrade controls on compressors $5,084 - $5,084
137,778
kWh
- - -
05 2.4131: Size electric motors for peak operating efficiency $8,999 $27,500 $5,018
136,000
kWh
$3,981
-
kW-mo/yr
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $20,158 $10,250 $16,068
435,460
kWh
$4,089
-
kW-mo/yr
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $46,176 $10,642 $34,268
928,676
kWh
$11,908
-
kW-mo/yr
- -
08 2.1113: Reduce combustion air flow to optimum $127,574 $25,000 - - - $127,574
-
MMBtu
09 3.8126: Use flue gas recuperation to reduce voc $79,353 $32,100 - - - $79,353
-
MMBtu
TOTAL RECOMMENDED $324,148 $166,998 $60,938
1,651,428
kWh
$20,134
-
kW-mo/yr
$33,277 $209,799
-
MMBtu
TOTAL IMPLEMENTED $150,771 $52,992 $55,421
1,501,914
kWh
$15,997
-
kW-mo/yr
- $79,353
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs