matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OK0756 #03 Y:2007 | 03 | 2007 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,491 | $1,000 | |
| OK0756 #02 Y:2007 | 02 | 2007 | Install / repair insulation on steam lines | $31,429 | $11,000 | |
| OK0756 #01 Y:2007 | 01 | 2007 | Begin a practice of predictive / preventative maintenance | $2,140 | $200 | |
| SF0351 #12 Y:2007 | 12 | 2007 | Utilize higher efficiency lamps and/or ballasts | $23,836 | $93,064 | |
| SF0351 #11 Y:2007 | 11 | 2007 | Insulate bare equipment | $493 | $979 | |
| SF0351 #10 Y:2007 | 10 | 2007 | Use adjustable frequency drive or multiple speed motors on existing system | $1,144 | $1,792 | |
| SF0351 #09 Y:2007 | 09 | 2007 | Reduce excessive boiler blowdown | $1,877 | $2,802 | |
| SF0351 #08 Y:2007 | 08 | 2007 | Insulate bare equipment | $685 | $503 | |
| SF0351 #07 Y:2007 | 07 | 2007 | Utilize controls to operate equipment only when needed | $1,173 | $228 | |
| SF0351 #06 Y:2007 | 06 | 2007 | Install occupancy sensors | $2,396 | $290 | |
| SF0351 #05 Y:2007 | 05 | 2007 | Insulate bare equipment | $584 | - | |
| SF0351 #04 Y:2007 | 04 | 2007 | Utilize controls to operate equipment only when needed | $1,173 | - | |
| SF0351 #03 Y:2007 | 03 | 2007 | Reduce the pressure of compressed air to the minimum required | $3,240 | $150 | |
| SF0351 #02 Y:2007 | 02 | 2007 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,336 | - | |
| SF0351 #01 Y:2007 | 01 | 2007 | Repair and eliminate steam leaks | $3,571 | - | |
| TT0015 #05 Y:2007 | 05 | 2007 | Utilize higher efficiency lamps and/or ballasts | $3,011 | $16,913 | |
| TT0015 #04 Y:2007 | 04 | 2007 | Utilize higher efficiency lamps and/or ballasts | $33,236 | $99,598 | |
| TT0015 #03 Y:2007 | 03 | 2007 | Repair or replace steam traps | $2,000 | $1,600 | |
| TT0015 #02 Y:2007 | 02 | 2007 | Re-use or recycle hot or cold process exhaust air | $17,800 | $35,600 | |
| TT0015 #01 Y:2007 | 01 | 2007 | Optimize plant power factor | $8,343 | $10,000 |