Assessment Year | 2008 |
---|---|
Principal Product | Elastomeric Rubber Products |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
160,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $194,471 | 1,630,247 |
kWh
|
$0.12 |
Electricity Demand | $31,245 | 7,072 |
kW-mo/yr
|
$4.42 |
Electricity Fees | $3,869 | - |
|
- |
Natural Gas | $279,459 | 30,681 |
MMBtu
|
$9.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $43,508 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,743 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $3,571 | - | - | - |
$3,571
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,336 | - |
$3,336
31,991
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,240 | $150 |
$2,785
23,346
kWh
|
$455
-
kW-mo/yr
|
- | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $1,173 | - |
$1,173
6,837
kWh
|
- | - | |
05 | 2.2511: Insulate bare equipment | $584 | - |
$584
4,900
kWh
|
- | - | |
06 | 2.7135: Install occupancy sensors | $2,396 | $290 |
$1,941
16,268
kWh
|
$455
-
kW-mo/yr
|
- | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $1,173 | $228 |
$1,173
6,837
kWh
|
- | - | |
08 | 2.2511: Insulate bare equipment | $685 | $503 | - | - |
$685
-
MMBtu
|
|
09 | 2.1241: Reduce excessive boiler blowdown | $1,877 | $2,802 | - | - |
$1,877
-
MMBtu
|
|
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,144 | $1,792 |
$1,144
9,587
kWh
|
- | - | |
11 | 2.2511: Insulate bare equipment | $493 | $979 | - | - |
$493
-
MMBtu
|
|
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $23,836 | $93,064 |
$19,928
167,057
kWh
|
$3,908
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $43,508 | $99,808 |
$32,064
266,823
kWh
|
$4,818
-
kW-mo/yr
|
$6,626
-
MMBtu
|
||
TOTAL IMPLEMENTED | $30,743 | $93,064 |
$23,264
199,048
kWh
|
$3,908
-
kW-mo/yr
|
$3,571
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs