Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,007

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Other rubber product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UD1072 #03 Y:2023 Install / repair insulation on condensate lines $63 $216
UD1072 #02 Y:2023 Install / repair insulation on steam lines $3,199 $864
UD1072 #01 Y:2023 Turn off equipment during breaks, reduce operating time $5,741 $5,000
UF0602 #10 Y:2023 Level one – add communication using iiot devices to existing control system to modify operations $215,016 -
UF0602 #09 Y:2023 Level zero – install control systems for existing equipment $341,860 $20,000
UF0602 #08 Y:2023 Lower light fixtures in high ceiling areas $13,084 $4,788
UF0602 #07 Y:2023 Utilize energy-efficient belts and other improved mechanisms $26,608 -
UF0602 #06 Y:2023 Use solar heat to make electricty $72,743 $322,608
UF0602 #05 Y:2023 Make ice during off peak hours for cooling $117,532 $250,000
UF0602 #04 Y:2023 Use most efficient type of electric motors $268,820 $137,250
UF0602 #03 Y:2023 Use or replace with energy efficient substitutes $339,285 $786,250
UF0602 #02 Y:2023 Install adequate dryers on air lines to eliminate blowdown $389,519 $50,482
UF0602 #01 Y:2023 Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $848,231 $3,118,500
UD1069 #08 Y:2023 Cover open tanks $42 $2,000
UD1069 #07 Y:2023 Use closed cycle process to minimize waste water production $51,914 $75,982
UD1069 #06 Y:2023 Install occupancy sensors $1,372 $1,389
UD1069 #05 Y:2023 Upgrade controls on compressors $1,799 -
UD1069 #04 Y:2023 Eliminate or reduce compressed air usage $2,894 $1,403
UD1069 #03 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $4,461 $952
UD1069 #02 Y:2023 Utilize energy-efficient belts and other improved mechanisms $3,796 $300