Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,085

matching recommendations
$
$
ARC 2+ Digits Required
NAICS All other plastics product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MI0473 #06 Y:2026 Clean or color roof to reduce solar load $5,599 $23,200
MI0473 #05 Y:2026 Install vinyl strip / high speed / air curtain doors $625 $1,200
MI0473 #04 Y:2026 Turn off equipment when not in use $2,046 $2,600
MI0473 #03 Y:2026 Use separate switches on perimeter lighting which may be turned off when natural light is available $253 $80
MI0473 #02 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $7,098 $1,980
MI0473 #01 Y:2026 Use power during off-peak periods $3,799 -
MS0470 #07 Y:2026 Chill water to the highest temperature possible $126 -
MS0470 #06 Y:2026 Reduce space conditioning during non-working hours $6,122 -
MS0470 #05 Y:2026 Separate and recycle scrap metal to foundry or for sale $10 -
MS0470 #04 Y:2026 Utilize higher efficiency lamps and/or ballasts $979 $1,323
MS0470 #03 Y:2026 Reduce the pressure of compressed air to the minimum required $50 -
MS0470 #02 Y:2026 Install occupancy sensors $491 $2,310
MS0470 #01 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $159 $540
UC2603 #11 Y:2026 Develop standard procedures to improve internal yields $20,020 $3,100
UC2603 #10 Y:2026 Modify startup/shutdown times $10,400 $3,600
UC2603 #09 Y:2026 Eliminate or reduce compressed air usage $3,406 $2,250
UC2603 #08 Y:2026 Utilize higher efficiency lamps and/or ballasts $2,596 $16,800
UC2603 #07 Y:2026 Utilize higher efficiency lamps and/or ballasts $1,471 $10,650
UC2603 #06 Y:2026 Install occupancy sensors $2,195 $7,200
UC2603 #05 Y:2026 Insulate bare equipment $507 $800