ITAC Assessment: NT0047
ITAC logo
ITAC Assessment: NT0047
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Rigid plastic containers for food and beverage
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 296
Plant Area 415,000
ft2
Annual Production 4,446,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $8,589,464 110,911,354
kWh
Electricity Fees $4,477 -
Natural Gas $190,432 21,659
MMBtu
Waste Disposal Costs
Water Usage $438,674 57,551
Tgal
TOTAL YEARLY COSTS $9,223,048
RECOMMENDED SAVINGS* $462,505 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $166,705 $320,438 $24,015
310,276
kWh
- $142,689
02 2.2625: Chill water to the highest temperature possible $89,410 - $89,410
1,155,166
kWh
- -
03 2.4322: Use or replace with energy efficient substitutes $87,586 $176,167 $87,586
1,131,606
kWh
- -
04 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $61,852 $120,692 $61,852
799,122
kWh
- -
05 2.7232: Replace existing hvac unit with high efficiency model $26,918 $27,300 $1,063
13,736
kWh
- $25,855
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $25,099 $4,224 $25,099
324,275
kWh
- -
07 2.1233: Analyze flue gas for proper air/fuel ratio $4,083 $1,434 - $4,083
-
MMBtu
-
08 2.7224: Reduce space conditioning during non-working hours $852 - $852
11,005
kWh
- -
TOTAL RECOMMENDED $462,505 $650,254 $289,878
3,745,186
kWh
$4,083
-
MMBtu
$168,544
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs