| Assessment Year | 1996 |
|---|---|
| Principal Product | Lead Products |
| NAICS |
n/a
|
| SIC | 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum |
| Sales Range | $10 M to 50M |
| # of Employees | 41 |
| Plant Area |
48,000
ft2
|
| Annual Production | 39,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,623 | 2,208,382 |
kWh
|
$0.030 |
| Electricity Demand | $9,462 | 6,564 |
kW-mo/yr
|
$1.44 |
| Electricity Fees | $3,136 | - |
|
- |
| Natural Gas | $56,821 | 11,009 |
MMBtu
|
$5.16 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,151 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,578 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $227 | - |
$195
6,448
kWh
|
$32
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2514: Cover open tanks | $4,287 | $540 | - | - | - |
$4,287
-
MMBtu
|
- | - | |
| 03 | 3.4115: Recover and reuse cooling water | $3,097 | $4,300 |
$(-114.0)
(-3,810)
kWh
|
$(-48.0)
-
kW-mo/yr
|
- | - |
$2,581
-
Tgal
|
$678
-
Tgal
|
|
| 04 | 2.3212: Optimize plant power factor | $2,286 | $4,800 | - | - | $2,286 | - | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,254 | $7,414 |
$1,057
35,756
kWh
|
$197
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $11,151 | $17,054 |
$1,138
38,394
kWh
|
$181
-
kW-mo/yr
|
$2,286 |
$4,287
-
MMBtu
|
$2,581
-
Tgal
|
$678
-
Tgal
|
||
| TOTAL IMPLEMENTED | $4,578 | $11,714 |
$1,138
38,394
kWh
|
$181
-
kW-mo/yr
|
- | - |
$2,581
-
Tgal
|
$678
-
Tgal
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs