ITAC Assessment: OR0257
ITAC logo
ITAC Assessment: OR0257
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Lead Products
NAICS
n/a
SIC 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum
Sales Range $10
M
to 50
M
# of Employees 41
Plant Area 48,000
ft2
Annual Production 39,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,623 2,208,382
kWh
Electricity Demand $9,462 6,564
kW-mo/yr
Electricity Fees $3,136 -
Natural Gas $56,821 11,009
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,151 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,578

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Water Consumption Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $227 - $195
6,448
kWh
$32
-
kW-mo/yr
- - - -
02 2.2514: Cover open tanks $4,287 $540 - - - $4,287
-
MMBtu
- -
03 3.4115: Recover and reuse cooling water $3,097 $4,300 $(-114.0)
(-3,810)
kWh
$(-48.0)
-
kW-mo/yr
- - $2,581
-
Tgal
$678
-
Tgal
04 2.3212: Optimize plant power factor $2,286 $4,800 - - $2,286 - - -
05 2.4133: Use most efficient type of electric motors $1,254 $7,414 $1,057
35,756
kWh
$197
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $11,151 $17,054 $1,138
38,394
kWh
$181
-
kW-mo/yr
$2,286 $4,287
-
MMBtu
$2,581
-
Tgal
$678
-
Tgal
TOTAL IMPLEMENTED $4,578 $11,714 $1,138
38,394
kWh
$181
-
kW-mo/yr
- - $2,581
-
Tgal
$678
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs