Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

514

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Paper bag and coated and treated paper manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
TT0100 #03 Y:2012 Utilize higher efficiency lamps and/or ballasts $830 $4,500
TT0100 #02 Y:2012 Install occupancy sensors $407 $150
TT0100 #01 Y:2012 Eliminate leaks in inert gas and compressed air lines/ valves $5,700 $3,000
MAS030 #06 Y:2012 Lower temperature during the winter season and vice-versa $1,098 $500
MAS030 #05 Y:2012 Install occupancy sensors $2,333 $4,400
MAS030 #04 Y:2012 Reduce the pressure of compressed air to the minimum required $2,379 -
MAS030 #03 Y:2012 Reduce the pressure of compressed air to the minimum required $3,092 -
MAS030 #02 Y:2012 Minimize operation of equipment maintained in standby condition $5,241 $1,500
MAS030 #01 Y:2012 Minimize operation of equipment maintained in standby condition $8,427 $2,500
NC0465 #11 Y:2012 Minimize boiler blowdown with better feedwater treatment $1,007 $1,000
NC0465 #10 Y:2012 Insulate feedwater tank $464 $1,150
NC0465 #09 Y:2012 Increase amount of condensate returned $2,179 $1,000
NC0465 #08 Y:2012 Analyze flue gas for proper air/fuel ratio $2,343 $1,200
NC0465 #07 Y:2012 Use heat from boiler blowdown to preheat boiler feed water $7,419 $16,000
NC0465 #06 Y:2012 Increase amount of condensate returned $2,959 $3,000
NC0465 #05 Y:2012 Reduce excessive boiler blowdown $512 -
NC0465 #04 Y:2012 Utilize higher efficiency lamps and/or ballasts $26,645 $45,006
NC0465 #03 Y:2012 Recover waste heat from equipment $5,615 $10,250
NC0465 #02 Y:2012 Reduce the pressure of compressed air to the minimum required $2,440 $200
NC0465 #01 Y:2012 Eliminate leaks in inert gas and compressed air lines/ valves $807 $400