Assessment Year | 2012 |
---|---|
Principal Product | Adhesive tapes |
NAICS | 322220: Paper Bag and Coated and Treated Paper Manufacturing |
SIC | 2672: Coated and Laminated Paper, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
125,000
ft2
|
Annual Production | 2,700,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $331,125 | 7,938,000 |
kWh
|
$0.042 |
Electricity Demand | $145,155 | 14,301 |
kW-mo/yr
|
$10.15 |
Natural Gas | $195,482 | 32,205 |
MMBtu
|
$6.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $52,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,916 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $807 | $400 |
$1,108
26,580
kWh
|
$539
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,440 | $200 |
$1,641
39,363
kWh
|
$799
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $5,615 | $10,250 |
$(-124.0)
(-2,984)
kWh
|
$(-61.0)
-
kW-mo/yr
|
$5,800
-
MMBtu
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,645 | $45,006 |
$17,090
409,836
kWh
|
$8,326
-
kW-mo/yr
|
- | - | $1,229 | - | |
05 | 2.1241: Reduce excessive boiler blowdown | $512 | - | - | - |
$436
-
MMBtu
|
- | - |
$76
-
Tgal
|
|
06 | 2.2121: Increase amount of condensate returned | $2,959 | $3,000 | - | - |
$2,052
-
MMBtu
|
- | - |
$907
-
Tgal
|
|
07 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $7,419 | $16,000 | - | - |
$7,419
-
MMBtu
|
- | - | - | |
08 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,343 | $1,200 | - | - |
$2,343
-
MMBtu
|
- | - | - | |
09 | 2.2121: Increase amount of condensate returned | $2,179 | $1,000 | - | - |
$2,179
-
MMBtu
|
- | - | - | |
10 | 2.2123: Insulate feedwater tank | $464 | $1,150 | - | - |
$464
-
MMBtu
|
- | - | - | |
11 | 2.1242: Minimize boiler blowdown with better feedwater treatment | $1,007 | $1,000 | - | - |
$261
-
MMBtu
|
- | $700 |
$46
-
Tgal
|
|
TOTAL RECOMMENDED | $52,390 | $79,206 |
$19,715
472,795
kWh
|
$9,603
-
kW-mo/yr
|
$20,954
-
MMBtu
|
$(-600.0) | $1,689 |
$1,029
-
Tgal
|
||
TOTAL IMPLEMENTED | $36,916 | $52,756 |
$18,198
436,416
kWh
|
$8,865
-
kW-mo/yr
|
$7,735
-
MMBtu
|
$(-600.0) | $1,689 |
$1,029
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs