Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

460

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Paper mills
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
LE0583 #07 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $9,189 $49,500
LE0583 #06 Y:2024 Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $1,627,510 $8,755,000
LE0583 #05 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $27,716 $10,250
LE0583 #04 Y:2024 Use optimum size and capacity equipment $19,014 $7,000
LE0583 #03 Y:2024 Recover heat from exhausted steam, hot air or hot water $344,366 $63,000
LE0583 #02 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $23,430 $2,300
LE0583 #01 Y:2024 Reduce the pressure of compressed air to the minimum required $9,486 -
UA0278 #08 Y:2023 Install occupancy sensors $1,770 $1,055
UA0278 #07 Y:2023 Install compressor air intakes in coolest locations $777 $4,000
UA0278 #06 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $2,416 $8,163
UA0278 #05 Y:2023 Reduce the pressure of compressed air to the minimum required $5,935 $1,000
UA0278 #04 Y:2023 Utilize energy-efficient belts and other improved mechanisms $7,819 $1,680
UA0278 #03 Y:2023 Install timers and/or thermostats $9,308 $327
UA0278 #02 Y:2023 Recover waste heat from equipment $61,473 $64,976
UA0278 #01 Y:2023 Meter recycled water (to reduce sewer charges) $83,920 $6,036
UA0272 #04 Y:2023 Optimize plant power factor $6,577 $7,065
UA0272 #03 Y:2023 Utilize energy-efficient belts and other improved mechanisms $5,741 $1,120
UA0272 #02 Y:2023 Utilize higher efficiency lamps and/or ballasts $7,415 $5,352
UA0272 #01 Y:2023 Install occupancy sensors $10,163 $4,516
UW2304 #05 Y:2023 Install occupancy sensors $231 $332