Assessment Year | 2024 |
---|---|
Principal Product | paper products |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | $50 M to 100M |
# of Employees | 204 |
Plant Area |
500,000
ft2
|
Annual Production | 65,000
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,525,657 | 56,969,343 |
kWh
|
$0.062 |
Electricity Demand | $483,388 | 78,050 |
kW-mo/yr
|
$6.19 |
Electricity Fees | $1,079,245 | - |
|
- |
Natural Gas | $3,776,541 | 837,218 |
MMBtu
|
$4.51 |
TOTAL YEARLY COSTS | $8,864,831 | |||
RECOMMENDED SAVINGS* | $2,060,711 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,486 | - |
$8,341
134,534
kWh
|
$1,145
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $23,430 | $2,300 |
$20,604
332,337
kWh
|
$2,826
-
kW-mo/yr
|
- | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $344,366 | $63,000 |
$(-140,841.0)
(-2,271,629)
kWh
|
$(-1,604.0)
-
kW-mo/yr
|
$486,811
-
MMBtu
|
|
04 | 2.4323: Use optimum size and capacity equipment | $19,014 | $7,000 |
$19,014
306,685
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,716 | $10,250 |
$24,373
393,120
kWh
|
$3,343
-
kW-mo/yr
|
- | |
06 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $1,627,510 | $8,755,000 |
$3,385,200
54,600,000
kWh
|
$482,820
-
kW-mo/yr
|
$(-2,240,510.0)
-
MMBtu
|
|
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,189 | $49,500 |
$8,081
130,341
kWh
|
$1,108
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $2,060,711 | $8,887,050 |
$3,324,772
53,625,388
kWh
|
$489,638
-
kW-mo/yr
|
$(-1,753,699.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs