376
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| DL0052 #05 Y:2010 | 05 | 2010 | Utilize controls to operate equipment only when needed | $12,940 | $1,500 | |
| DL0052 #04 Y:2010 | 04 | 2010 | Eliminate leaks in inert gas and compressed air lines/ valves | $15,250 | $9,000 | |
| DL0052 #03 Y:2010 | 03 | 2010 | Utilize higher efficiency lamps and/or ballasts | $25,100 | $24,000 | |
| DL0052 #02 Y:2010 | 02 | 2010 | Recycle air for heating, ventilation and air conditioning | $53,946 | $10,848 | |
| DL0052 #01 Y:2010 | 01 | 2010 | Avoid introducing hot, humid, or dirty air into hvac system | $143,000 | $81,500 | |
| MA0653 #06 Y:2009 | 06 | 2009 | Use adjustable frequency drive or multiple speed motors on existing system | $2,375 | $6,125 | |
| MA0653 #05 Y:2009 | 05 | 2009 | Insulate bare equipment | $2,840 | $7,510 | |
| MA0653 #04 Y:2009 | 04 | 2009 | Close off unneeded steam lines | $3,551 | $500 | |
| MA0653 #03 Y:2009 | 03 | 2009 | Reduce ventilation air | $16,188 | $752 | |
| MA0653 #02 Y:2009 | 02 | 2009 | Install smaller boiler (increase high fire duty cycle) | $37,210 | $68,000 | |
| MA0653 #01 Y:2009 | 01 | 2009 | Install smaller boiler (increase high fire duty cycle) | $110,550 | $270,000 | |
| LE0291 #11 Y:2009 | 11 | 2009 | Install occupancy sensors | $3,572 | $1,050 | |
| LE0291 #10 Y:2009 | 10 | 2009 | Utilize higher efficiency lamps and/or ballasts | $5,803 | $19,856 | |
| LE0291 #09 Y:2009 | 09 | 2009 | Utilize higher efficiency lamps and/or ballasts | $26,236 | $81,400 | |
| LE0291 #08 Y:2009 | 08 | 2009 | Reduce the pressure of compressed air to the minimum required | $1,836 | $560 | |
| LE0291 #07 Y:2009 | 07 | 2009 | Install vinyl strip / high speed / air curtain doors | $1,975 | $3,460 | |
| LE0291 #06 Y:2009 | 06 | 2009 | Install timers and/or thermostats | $2,837 | $125 | |
| LE0291 #05 Y:2009 | 05 | 2009 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,439 | $1,600 | |
| LE0291 #04 Y:2009 | 04 | 2009 | Utilize energy-efficient belts and other improved mechanisms | $6,457 | $1,120 | |
| LE0291 #03 Y:2009 | 03 | 2009 | Reschedule plant operations or reduce load to avoid peaks | $15,557 | $2,500 |