Assessment Year | 2009 |
---|---|
Principal Product | Coated and finished woven and non-woven materials |
NAICS | 313310: Textile and Fabric Finishing Mills |
SIC | 2261: Finishers of Broadwoven Fabrics of Cotton |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
200,000
ft2
|
Annual Production | 12,000
thousand feet
|
Production Hrs. Annual | 1,440
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $123,418 | 1,173,600 |
kWh
|
$0.11 |
Electricity Demand | $92,871 | 7,508 |
kW-mo/yr
|
$12.37 |
Electricity Fees | $8,608 | - |
|
- |
Natural Gas | $347,467 | 25,094 |
MMBtu
|
$13.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $172,714 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,028 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $110,550 | $270,000 | - |
$110,550
-
MMBtu
|
|
02 | 2.1223: Install smaller boiler (increase high fire duty cycle) | $37,210 | $68,000 | - |
$37,210
-
MMBtu
|
|
03 | 2.7314: Reduce ventilation air | $16,188 | $752 |
$2,453
23,365
kWh
|
$13,735
-
MMBtu
|
|
04 | 2.2153: Close off unneeded steam lines | $3,551 | $500 | - |
$3,551
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $2,840 | $7,510 | - |
$2,840
-
MMBtu
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,375 | $6,125 |
$2,375
22,622
kWh
|
- | |
TOTAL RECOMMENDED | $172,714 | $352,887 |
$4,828
45,987
kWh
|
$167,886
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,028 | $8,262 |
$2,453
23,365
kWh
|
$16,575
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs