Assessment Year | 1996 |
---|---|
Principal Product | Metal Platings, Fabricated Metal Furniture Parts, Baby Furni |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 48 |
Plant Area |
140,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 2,375
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,685 | 1,875,440 |
kWh
|
$0.061 |
Electricity Demand | $64,498 | 6,720 |
kW-mo/yr
|
$9.60 |
Electricity Fees | $879 | - |
|
- |
Natural Gas | $75,907 | 23,393 |
MMBtu
|
$3.24 |
Fuel Oil #2 | $8,845 | 1,749 |
MMBtu
|
$5.06 |
Fuel Oil #6 | $101,506 | 29,532 |
MMBtu
|
$3.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,021 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7442: Keep doors and windows shut when not on use | $7,468 | $4,677 |
$(-212.0)
(-3,517)
kWh
|
- |
$3,546
-
MMBtu
|
$4,134
-
MMBtu
|
- | - | - | - | |
02 | 2.4224: Upgrade controls on compressors | $2,121 | $1,100 |
$2,121
31,360
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $329 | - |
$363
5,275
kWh
|
- | - | - |
$(-34.0)
-
gal
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $456 | $157 |
$456
6,741
kWh
|
- | - | - | - | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $444 | $290 | - | - |
$141
-
MMBtu
|
$303
-
MMBtu
|
- | - | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $683 | $1,590 | - | - |
$240
-
MMBtu
|
$443
-
MMBtu
|
- | - | - | - | |
07 | 2.2122: Install / repair insulation on condensate lines | $310 | $1,888 | - | - |
$310
-
MMBtu
|
- | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,823 | $47,265 |
$5,076
77,667
kWh
|
$3,747
-
kW-mo/yr
|
- | - | - | - | - | - | |
09 | 3.4145: Use magnetic technology to treat water | $9,036 | $6,000 | - | - | - | - | - | - | - | $9,036 | |
10 | 3.7391: Implement a maintenance program to keep racks and tanks free of rust, cracks, or corrosion | $1,125 | $400 | - | - | - | - | - | - | $1,125 | - | |
11 | 3.6112: Use filter and drying oven to reduce sludge volume | $10,877 | $31,500 | - | - |
$(-604.0)
-
MMBtu
|
$(-703.0)
-
MMBtu
|
- |
$12,184
-
lb
|
- | - | |
12 | 3.5242: Recover metals from spent solutions and recycle | $28,830 | $97,000 | - | - | - | - | - | - | $28,830 | - | |
TOTAL RECOMMENDED | $70,502 | $191,867 |
$7,804
117,526
kWh
|
$3,747
-
kW-mo/yr
|
$3,633
-
MMBtu
|
$4,177
-
MMBtu
|
$(-34.0)
-
gal
|
$12,184
-
lb
|
$29,955 | $9,036 | ||
TOTAL IMPLEMENTED | $3,021 | $1,547 |
$2,577
38,101
kWh
|
- |
$141
-
MMBtu
|
$303
-
MMBtu
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #6 Savings | Other Liquid (haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs