| Assessment Year | 2009 |
|---|---|
| Principal Product | High Performance Engineered Yarn |
| NAICS | 313310: Textile and Fabric Finishing Mills |
| SIC | 2295: Coated Fabrics, Not Rubberized |
| Sales Range | $10 M to 50M |
| # of Employees | 107 |
| Plant Area |
70,000
ft2
|
| Annual Production | 10,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $290,593 | 5,475,432 |
kWh
|
$0.053 |
| Electricity Demand | $126,006 | 14,824 |
kW-mo/yr
|
$8.50 |
| Natural Gas | $22,730 | 1,602 |
MMBtu
|
$14.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $124,279 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,850 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2314: Replace heat treating oven with more efficient unit | $32,078 | $50,000 |
$23,161
437,004
kWh
|
$8,917
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $22,489 | $510 |
$22,489
424,323
kWh
|
- | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $15,557 | $2,500 | - |
$15,557
-
kW-mo/yr
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,457 | $1,120 |
$4,935
93,209
kWh
|
$1,522
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,439 | $1,600 |
$4,156
78,428
kWh
|
$1,283
-
kW-mo/yr
|
- | |
| 06 | 2.7261: Install timers and/or thermostats | $2,837 | $125 |
$2,397
45,230
kWh
|
- |
$440
-
MMBtu
|
|
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,975 | $3,460 |
$1,975
33,870
kWh
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,836 | $560 |
$1,403
26,466
kWh
|
$433
-
kW-mo/yr
|
- | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $26,236 | $81,400 |
$20,226
367,860
kWh
|
$6,010
-
kW-mo/yr
|
- | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,803 | $19,856 |
$4,690
55,801
kWh
|
$1,113
-
kW-mo/yr
|
- | |
| 11 | 2.7135: Install occupancy sensors | $3,572 | $1,050 |
$3,572
67,392
kWh
|
- | - | |
| TOTAL RECOMMENDED | $124,279 | $162,181 |
$89,004
1,629,583
kWh
|
$34,835
-
kW-mo/yr
|
$440
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $23,850 | $4,180 |
$6,338
119,675
kWh
|
$17,512
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs