ITAC Assessment: LE0291
ITAC logo
ITAC Assessment: LE0291
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product High Performance Engineered Yarn
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $10
M
to 50
M
# of Employees 107
Plant Area 70,000
ft2
Annual Production 10,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $290,593 5,475,432
kWh
Electricity Demand $126,006 14,824
kW-mo/yr
Natural Gas $22,730 1,602
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $124,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,850

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2314: Replace heat treating oven with more efficient unit $32,078 $50,000 $23,161
437,004
kWh
$8,917
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $22,489 $510 $22,489
424,323
kWh
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $15,557 $2,500 - $15,557
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,457 $1,120 $4,935
93,209
kWh
$1,522
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,439 $1,600 $4,156
78,428
kWh
$1,283
-
kW-mo/yr
-
06 2.7261: Install timers and/or thermostats $2,837 $125 $2,397
45,230
kWh
- $440
-
MMBtu
07 2.7447: Install vinyl strip / high speed / air curtain doors $1,975 $3,460 $1,975
33,870
kWh
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $1,836 $560 $1,403
26,466
kWh
$433
-
kW-mo/yr
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $26,236 $81,400 $20,226
367,860
kWh
$6,010
-
kW-mo/yr
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $5,803 $19,856 $4,690
55,801
kWh
$1,113
-
kW-mo/yr
-
11 2.7135: Install occupancy sensors $3,572 $1,050 $3,572
67,392
kWh
- -
TOTAL RECOMMENDED $124,279 $162,181 $89,004
1,629,583
kWh
$34,835
-
kW-mo/yr
$440
-
MMBtu
TOTAL IMPLEMENTED $23,850 $4,180 $6,338
119,675
kWh
$17,512
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs