Assessment Year | 1997 |
---|---|
Principal Product | Commercial and Domestic Dryers |
NAICS |
n/a
|
SIC | 3582: Commercial Laundry, Drycleaning, and Pressing Machines |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
252,000
ft2
|
Annual Production | 350,000
pieces
|
Production Hrs. Annual | 5,005
hrs
|
Location (State) | Arkansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $261,534 | 7,536,929 |
kWh
|
$0.035 |
Electricity Demand | $216,375 | 19,954 |
kW-mo/yr
|
$10.84 |
Natural Gas | $195,170 | 57,967 |
MMBtu
|
$3.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $80,716 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,236 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,776 | $1,266 |
$1,525
43,669
kWh
|
$1,251
-
kW-mo/yr
|
- | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $3,333 | $2,110 |
$1,932
55,100
kWh
|
$1,401
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,376 | $340 |
$3,659
105,803
kWh
|
$2,717
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $8,071 | $11,370 |
$4,501
128,664
kWh
|
$3,570
-
kW-mo/yr
|
- | - | - | |
05 | 3.8142: Distill contaminated solvents for reuse | $11,480 | $11,000 | - | - |
$11,480
-
gal
|
- | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $240 | - | - | - | - |
$240
-
lb
|
- | |
07 | 3.5217: Reuse / recycle/ sell paper products | $1,440 | - | - | - | - |
$1,440
-
lb
|
- | |
08 | 4.423: Move product using mechanical means | $30,000 | $25,000 | - | - | - | - | $30,000 | |
09 | 4.651: Install back-up equipment | $17,000 | $9,000 | - | - | - | - | $17,000 | |
TOTAL RECOMMENDED | $80,716 | $60,086 |
$11,617
333,236
kWh
|
$8,939
-
kW-mo/yr
|
$11,480
-
gal
|
$1,680
-
lb
|
$47,000 | ||
TOTAL IMPLEMENTED | $39,236 | $24,086 |
$11,617
333,236
kWh
|
$8,939
-
kW-mo/yr
|
- |
$1,680
-
lb
|
$17,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs