ITAC Assessment: LM0050
ITAC logo
ITAC Assessment: LM0050
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product canned juice
NAICS 311411: Frozen Fruit, Juice, and Vegetable Manufacturing
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 64,000
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 4,125
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $302,645 2,521,742
kWh
Electricity Demand $90,426 6,576
kW-mo/yr
Electricity Fees $20,817 -
Natural Gas $31,592 6,246
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $306,442 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $35,209

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
01 2.7144: Install spectral reflectors / delamp $16,417 $270 $13,250
113,928
kWh
$3,167
-
kW-mo/yr
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $606 $900 $521
4,481
kWh
$85
-
kW-mo/yr
- - - - -
03 2.4133: Use most efficient type of electric motors $3,032 $342 $2,251
19,349
kWh
$781
-
kW-mo/yr
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,993 $350 $5,589
48,066
kWh
$911
-
kW-mo/yr
- $(-507.0) - - -
05 2.4239: Eliminate or reduce compressed air usage $3,400 $280 $2,523
21,698
kWh
$877
-
kW-mo/yr
- - - - -
06 2.1232: Keep boiler tubes clean $552 $1,000 - - $552
-
MMBtu
- - - -
07 2.4226: Use / purchase optimum sized compressor $2,896 $2,669 $2,896
32,413
kWh
- - - - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $937 $2,580 $700
5,243
kWh
$237
-
kW-mo/yr
- - - - -
09 4.625: Develop standard operating procedures $19,825 $6,026 - - - - - - $19,825
10 4.321: Optimize production lot sizes and inventories $5,943 $1,000 - - - - $5,943 - -
11 4.431: Train operators for maximum operating efficiency $57,825 $12,920 - - - $57,825 - - -
12 4.131: Modify process to reduce material use/cost $25,000 $15,404 - - - - - $25,000 -
13 4.441: Install automatic packing equipment $62,400 $100,000 - - - $62,400 - - -
14 4.221: Use only amount of packaging material necessary $101,616 $150,000 $(-28,784.0)
(-247,500)
kWh
$(-10,008.0)
-
kW-mo/yr
- - $140,408 - -
TOTAL RECOMMENDED $306,442 $293,741 $(-1,054.0)
(-2,322)
kWh
$(-3,950.0)
-
kW-mo/yr
$552
-
MMBtu
$119,718 $146,351 $25,000 $19,825
TOTAL IMPLEMENTED $35,209 $11,045 $8,485
80,479
kWh
$911
-
kW-mo/yr
$552
-
MMBtu
$(-507.0) $5,943 - $19,825
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs