483
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UL2602 #07 Y:2026 | 07 | 2026 | Recover waste heat from equipment | $22,369 | $25,000 |
n/a
|
| UL2602 #06 Y:2026 | 06 | 2026 | Use solar heat to make electricty | $45,457 | $471,029 |
n/a
|
| UL2602 #05 Y:2026 | 05 | 2026 | Recover waste heat from equipment | $26,375 | $80,000 |
n/a
|
| UL2602 #04 Y:2026 | 04 | 2026 | Install / repair insulation on steam lines | $5,603 | $2,318 |
n/a
|
| UL2602 #03 Y:2026 | 03 | 2026 | Use adjustable frequency drive or multiple speed motors on existing system | $3,036 | $16,250 |
n/a
|
| UL2602 #02 Y:2026 | 02 | 2026 | Reduce the pressure of compressed air to the minimum required | $6,663 | - |
n/a
|
| UL2602 #01 Y:2026 | 01 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $6,840 | $1,337 |
n/a
|
| NL0118 #05 Y:2025 | 05 | 2025 | Utilize energy-efficient belts and other improved mechanisms | $634 | $608 |
n/a
|
| NL0118 #04 Y:2025 | 04 | 2025 | Reduce the pressure of compressed air to the minimum required | $636 | $165 |
n/a
|
| NL0118 #03 Y:2025 | 03 | 2025 | Meter waste water | $857 | $985 |
n/a
|
| NL0118 #02 Y:2025 | 02 | 2025 | Meter waste water | $3,352 | $1,575 |
n/a
|
| NL0118 #01 Y:2025 | 01 | 2025 | Recharge batteries on during off-peak demand periods | $15,441 | $550 |
n/a
|
| CI0053 #09 Y:2025 | 09 | 2025 | Recharge batteries on during off-peak demand periods | $6,854 | $200 |
n/a
|
| CI0053 #08 Y:2025 | 08 | 2025 | Use photocell controls | $14,804 | $4,000 |
n/a
|
| CI0053 #07 Y:2025 | 07 | 2025 | Utilize higher efficiency lamps and/or ballasts | $17,542 | $3,762 |
n/a
|
| CI0053 #06 Y:2025 | 06 | 2025 | Use most efficient type of electric motors | $26,465 | $20,000 |
n/a
|
| CI0053 #05 Y:2025 | 05 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $57,280 | $7,800 |
n/a
|
| CI0053 #04 Y:2025 | 04 | 2025 | Use optimum thickness insulation | $67,904 | $174,000 |
n/a
|
| CI0053 #03 Y:2025 | 03 | 2025 | Preheat combustion air with waste heat | $127,862 | $20,000 |
n/a
|
| CI0053 #02 Y:2025 | 02 | 2025 | Use solar heat to make electricty | $159,105 | $669,600 |
n/a
|