Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

240

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Frozen specialty food manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
DL0247 #09 Y:2024 Utilize a less expensive cooling method $116,551 $1,000,000
DL0247 #08 Y:2024 Replace existing chiller with high efficiency model $27,958 $200,000
DL0247 #07 Y:2024 Meter waste water $34,580 $145
DL0247 #06 Y:2024 Turn off equipment when not in use $993 -
DL0247 #05 Y:2024 Turn off equipment when not in use $399 -
DL0247 #04 Y:2024 Turn off steam / hot water lines leading to space heating units $1,592 -
DL0247 #03 Y:2024 Lower temperature during the winter season and vice-versa $1,671 -
DL0247 #02 Y:2024 Utilize controls to operate equipment only when needed $4,382 -
DL0247 #01 Y:2024 Reduce space conditioning during non-working hours $350 -
UU0259 #06 Y:2024 Install common header on compressors $3,995 $9,200
UU0259 #05 Y:2024 Store heated/ cooled water for use during peak demand periods $53,643 $33,000
UU0259 #04 Y:2024 Utilize higher efficiency lamps and/or ballasts $68,165 $110,030
UU0259 #03 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $205,038 $1,865,253
UU0259 #02 Y:2024 Use solar heat to make electricty $221,450 $2,473,450
UU0259 #01 Y:2024 Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat $3,866,540 $17,885,484
NL0099 #06 Y:2024 Change rate schedules or other changes in utility service $240 $35
NL0099 #05 Y:2024 Eliminate or reduce compressed air usage $6,201 $140
NL0099 #04 Y:2024 Use flue gases to heat process or service water $8,784 $35,100
NL0099 #03 Y:2024 Use waste heat from hot flue gases to preheat $102,668 $214,595
NL0099 #02 Y:2024 Optimize plant power factor $569,646 $74,000