| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OR0560 #08 Y:2010 | 08 | 2010 | Install occupancy sensors | $10,085 | $70,024 | |
| OR0560 #07 Y:2010 | 07 | 2010 | Recover waste heat from equipment | $36,273 | $3,637 | |
| OR0560 #06 Y:2010 | 06 | 2010 | Optimize plant power factor | $11,450 | $23,156 | |
| OR0560 #05 Y:2010 | 05 | 2010 | Utilize controls to operate equipment only when needed | $3,400 | $7,001 | |
| OR0560 #04 Y:2010 | 04 | 2010 | Chill water to the highest temperature possible | $11,768 | - | |
| OR0560 #03 Y:2010 | 03 | 2010 | Modify refrigeration system to operate at a lower pressure | $8,047 | - | |
| OR0560 #02 Y:2010 | 02 | 2010 | Re-arrange equipment layout to reduce handling costs | $37,651 | $90,666 | |
| OR0560 #01 Y:2010 | 01 | 2010 | Replace existing equipment with more suitable substitutes | $68,119 | $26,207 | |
| OR0558 #06 Y:2010 | 06 | 2010 | Modify refrigeration system to operate at a lower pressure | $930 | $1 | |
| OR0558 #05 Y:2010 | 05 | 2010 | Use solar heat to make electricty | $25,798 | $379,829 | |
| OR0558 #04 Y:2010 | 04 | 2010 | Install occupancy sensors | $14,738 | $120,911 | |
| OR0558 #03 Y:2010 | 03 | 2010 | Reduce the pressure of compressed air to the minimum required | $1,319 | $4,935 | |
| OR0558 #02 Y:2010 | 02 | 2010 | Eliminate leaks in inert gas and compressed air lines/ valves | $7,102 | $7,102 | |
| OR0558 #01 Y:2010 | 01 | 2010 | Modify refrigeration system to operate at a lower pressure | $6,602 | $2,965 | |
| OR0557 #09 Y:2010 | 09 | 2010 | Use solar heat to make electricty | $23,079 | $87,827 | |
| OR0557 #08 Y:2010 | 08 | 2010 | Install / repair insulation on steam lines | $615 | $353 | |
| OR0557 #07 Y:2010 | 07 | 2010 | Reduce the pressure of compressed air to the minimum required | $1,471 | $1,471 | |
| OR0557 #06 Y:2010 | 06 | 2010 | Utilize higher efficiency lamps and/or ballasts | $1,035 | $3,858 | |
| OR0557 #05 Y:2010 | 05 | 2010 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,655 | $1,655 | |
| OR0557 #04 Y:2010 | 04 | 2010 | Recover waste heat from equipment | $1,893 | $3,858 |