10,181
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| UF0640 #08 Y:2025 | 08 | 2025 | Meter recycled water (to reduce sewer charges) | $40,788 | $5,352 |
n/a
|
| UF0640 #07 Y:2025 | 07 | 2025 | Install turbulators | $747 | $3,000 |
n/a
|
| UF0640 #06 Y:2025 | 06 | 2025 | Improve combustion control capability | $868 | $1,400 |
n/a
|
| UF0640 #05 Y:2025 | 05 | 2025 | Increase amount of condensate returned | $1,007 | $1,670 |
n/a
|
| UF0640 #04 Y:2025 | 04 | 2025 | Utilize energy-efficient belts and other improved mechanisms | $1,691 | - |
n/a
|
| UF0640 #03 Y:2025 | 03 | 2025 | Reduce the pressure of compressed air to the minimum required | $1,993 | - |
n/a
|
| UF0640 #02 Y:2025 | 02 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $4,193 | $360 |
n/a
|
| UF0640 #01 Y:2025 | 01 | 2025 | Use demand controller or load shedder | $13,290 | $8,730 |
n/a
|
| LE0605 #06 Y:2025 | 06 | 2025 | Replace existing hvac unit with high efficiency model | $6,798 | $33,750 |
n/a
|
| LE0605 #05 Y:2025 | 05 | 2025 | Replace existing hvac unit with high efficiency model | $11,122 | $88,200 |
n/a
|
| LE0605 #04 Y:2025 | 04 | 2025 | Clean or color roof to reduce solar load | $2,453 | $7,474 |
n/a
|
| LE0605 #03 Y:2025 | 03 | 2025 | Install occupancy sensors | $425 | $375 |
n/a
|
| LE0605 #02 Y:2025 | 02 | 2025 | Utilize higher efficiency lamps and/or ballasts | $1,137 | $1,821 |
n/a
|
| LE0605 #01 Y:2025 | 01 | 2025 | Install timers and/or thermostats | $1,124 | $1,120 |
n/a
|
| NL0125 #06 Y:2025 | 06 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,881 | $3,000 |
n/a
|
| NL0125 #05 Y:2025 | 05 | 2025 | Use waste heat from hot flue gases to preheat | $184,176 | $1,561,000 |
n/a
|
| NL0125 #04 Y:2025 | 04 | 2025 | Use continuous processing | $515,427 | $123,656 |
n/a
|
| NL0125 #03 Y:2025 | 03 | 2025 | Reduce fluid flow rates | $862,950 | $672,300 |
n/a
|
| NL0125 #02 Y:2025 | 02 | 2025 | Add/modify equipment to improve drying process | $150,000 | $1,200,000 |
n/a
|
| NL0125 #01 Y:2025 | 01 | 2025 | Consolidate freight shipments and/or deliveries | $150,000 | $600,000 |
n/a
|