Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

48

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Foundation, structure, and building exterior contractors
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
IP7002 #07 Y:2023 Utilize higher efficiency lamps and/or ballasts $290 $916
IP7002 #06 Y:2023 Utilize higher efficiency lamps and/or ballasts $5,653 $7,466
IP7002 #05 Y:2023 Install vinyl strip / high speed / air curtain doors $517 $76
IP7002 #04 Y:2023 Eliminate or reduce compressed air usage $4,188 $225
IP7002 #03 Y:2023 Eliminate leaks in inert gas and compressed air lines/ valves $3,929 $205
IP7002 #02 Y:2023 Utilize energy-efficient belts and other improved mechanisms $8,165 $202
IP7002 #01 Y:2023 Reduce space conditioning during non-working hours $1,792 -
OK0845 #09 Y:2012 Optimize plant power factor $2,148 $7,526
OK0845 #08 Y:2012 Use radiant heater for spot heating $20,678 $90,000
OK0845 #07 Y:2012 Recover waste heat from equipment $1,780 $1,378
OK0845 #06 Y:2012 Use or replace with energy efficient substitutes $318 $1,584
OK0845 #05 Y:2012 Eliminate leaks in inert gas and compressed air lines/ valves $2,941 $550
OK0845 #04 Y:2012 Reduce the pressure of compressed air to the minimum required $1,058 -
OK0845 #03 Y:2012 Make a practice of turning off lights when not needed $2,271 $3,608
OK0845 #02 Y:2012 Install occupancy sensors $90 $366
OK0845 #01 Y:2012 Utilize higher efficiency lamps and/or ballasts $2,354 $12,299
OR0550 #09 Y:2009 Use optimum size and capacity equipment $9,660 $1,330
OR0550 #08 Y:2009 Upgrade controls on compressors $24,600 $7,540
OR0550 #07 Y:2009 Install adequate dryers on air lines to eliminate blowdown $1,600 -
OR0550 #06 Y:2009 Use / purchase optimum sized compressor $22,900 $12,750