Assessment Year | 2009 |
---|---|
Principal Product | Hardboard siding |
NAICS | 238170: Siding Contractors |
SIC | 1761: Roofing, Siding, and Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
350,000
ft2
|
Annual Production | 75,000,000
thousand feet
|
Production Hrs. Annual | 3,120
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,416,347 | 49,590,760 |
kWh
|
$0.049 |
Electricity Demand | $353 | 117 |
kW-mo/yr
|
$3.02 |
Natural Gas | $980,153 | 127,055 |
MMBtu
|
$7.71 |
Other Energy | $4,796,849 | 562,560 |
MMBtu
|
$8.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $580,948 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $457,667 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Other Energy Savings |
---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $435,946 | $2,900 | - |
$435,946
-
MMBtu
|
|
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,835 | - |
$3,835
81,017
kWh
|
- | |
03 | 2.2424: Use heat in flue gases to preheat products or materials | $60,786 | $20,000 | - |
$60,786
-
MMBtu
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,335 | $11,100 |
$5,335
106,009
kWh
|
- | |
05 | 2.4133: Use most efficient type of electric motors | $16,286 | $42,778 |
$16,286
338,336
kWh
|
- | |
06 | 2.4226: Use / purchase optimum sized compressor | $22,900 | $12,750 |
$22,900
591,000
kWh
|
- | |
07 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,600 | - |
$1,600
34,000
kWh
|
- | |
08 | 2.4224: Upgrade controls on compressors | $24,600 | $7,540 |
$24,600
525,000
kWh
|
- | |
09 | 2.4323: Use optimum size and capacity equipment | $9,660 | $1,330 |
$9,660
255,000
kWh
|
- | |
TOTAL RECOMMENDED | $580,948 | $98,398 |
$84,216
1,930,362
kWh
|
$496,732
-
MMBtu
|
||
TOTAL IMPLEMENTED | $457,667 | $45,678 |
$21,721
453,353
kWh
|
$435,946
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Other Energy Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs