ITAC Assessment: AS0559
ITAC logo
ITAC Assessment: AS0559
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product aerospace machined components
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 50,000
ft2
Annual Production 58,023
units
Production Hrs. Annual 6,160
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,235 1,553,360
kWh
Electricity Demand $20,641 5,708
kW-mo/yr
Electricity Fees $14,523 -
TOTAL YEARLY COSTS $158,399
RECOMMENDED SAVINGS* $50,668 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $19,170 $219,972 $18,822
232,375
kWh
$348
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $11,967 $325 $11,262
142,019
kWh
$705
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,376 $6,232 $3,680
46,401
kWh
$229
-
kW-mo/yr
$1,467
04 2.7226: Use computer programs to optimize hvac performance $4,898 $1,744 $4,314
54,368
kWh
$584
-
kW-mo/yr
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $4,469 $166 $4,172
52,605
kWh
$297
-
kW-mo/yr
-
06 2.7447: Install vinyl strip / high speed / air curtain doors $4,205 $248 $388
4,895
kWh
$3,817
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $320 $235 $296
3,730
kWh
$24
-
kW-mo/yr
-
08 2.7132: Install timers on light switches in little used areas $263 $660 $263
3,313
kWh
- -
TOTAL RECOMMENDED $50,668 $229,582 $43,197
539,706
kWh
$6,004
-
kW-mo/yr
$1,467
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs