| Assessment Year | 2023 |
|---|---|
| Principal Product | aerospace machined components |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 60 |
| Plant Area |
50,000
ft2
|
| Annual Production | 58,023
units
|
| Production Hrs. Annual | 6,160
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $123,235 | 1,553,360 |
kWh
|
$0.079 |
| Electricity Demand | $20,641 | 5,708 |
kW-mo/yr
|
$3.62 |
| Electricity Fees | $14,523 | - |
|
- |
| TOTAL YEARLY COSTS | $158,399 | |||
| RECOMMENDED SAVINGS* | $50,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $19,170 | $219,972 |
$18,822
232,375
kWh
|
$348
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,967 | $325 |
$11,262
142,019
kWh
|
$705
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,376 | $6,232 |
$3,680
46,401
kWh
|
$229
-
kW-mo/yr
|
$1,467 | |
| 04 | 2.7226: Use computer programs to optimize hvac performance | $4,898 | $1,744 |
$4,314
54,368
kWh
|
$584
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,469 | $166 |
$4,172
52,605
kWh
|
$297
-
kW-mo/yr
|
- | |
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,205 | $248 |
$388
4,895
kWh
|
$3,817
-
kW-mo/yr
|
- | |
| 07 | 2.7135: Install occupancy sensors | $320 | $235 |
$296
3,730
kWh
|
$24
-
kW-mo/yr
|
- | |
| 08 | 2.7132: Install timers on light switches in little used areas | $263 | $660 |
$263
3,313
kWh
|
- | - | |
| TOTAL RECOMMENDED | $50,668 | $229,582 |
$43,197
539,706
kWh
|
$6,004
-
kW-mo/yr
|
$1,467 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs