| Assessment Year | 2023 |
|---|---|
| Principal Product | Metal Roofing |
| NAICS | 238160: Roofing Contractors |
| SIC | 1761: Roofing, Siding, and Sheet Metal Work |
| Sales Range | $1 M to 5M |
| # of Employees | 15 |
| Plant Area |
25,000
ft2
|
| Annual Production | 300
ton
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,275 | 6,784 |
kWh
|
$0.19 | |
| Natural Gas | $4,115 | 622 |
MMBtu
|
$6.61 | |
| Other Energy | $8,789 | 136 |
MMBtu
|
$64.45 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,200 | 35 |
Tgal
|
$34.48 | |
| TOTAL YEARLY COSTS | $15,379 | ||||
| RECOMMENDED SAVINGS* | $24,534 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $16,079 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $1,792 | - |
$1,074
5,715
kWh
|
$718
-
MMBtu
|
|
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,165 | $202 |
$8,165
43,430
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,929 | $205 |
$3,929
20,899
kWh
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $4,188 | $225 |
$4,188
22,275
kWh
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $517 | $76 |
$517
2,751
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,653 | $7,466 |
$5,653
30,068
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $290 | $916 |
$290
1,542
kWh
|
- | |
| TOTAL RECOMMENDED | $24,534 | $9,090 |
$23,816
126,680
kWh
|
$718
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $16,079 | $7,972 |
$15,361
81,708
kWh
|
$718
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs