Assessment Year | 2002 |
---|---|
Principal Product | Cans, Can Parts, Can Bodies |
NAICS |
n/a
|
SIC | 3411: Metal Cans |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
175,000
ft2
|
Annual Production | 120,000,000
pieces
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $483,927 | 6,308,000 |
kWh
|
$0.077 |
Natural Gas | $68,066 | 10,392 |
MMBtu
|
$6.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,581 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $15,241 | $1,875 |
$15,241
198,651
kWh
|
- | - | - | |
02 | 2.2628: Utilize a less expensive cooling method | $1,124 | $525 |
$1,124
14,650
kWh
|
- | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,006 | $3,100 |
$5,006
65,251
kWh
|
- | - | - | |
04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $9,017 | $750 |
$9,017
121,302
kWh
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $5,013 | $444 |
$5,013
65,412
kWh
|
- | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,512 | $125 |
$7,512
97,909
kWh
|
- | - | - | |
07 | 3.5316: Contract a wood pallet recycling company | $2,700 | $100 | - | - |
$2,700
-
lb
|
- | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $6,968 | $2,500 | - |
$6,968
-
Tgal
|
- | - | |
09 | 4.652: Replace existing equipment with more suitable substitutes | $14,000 | $6,000 | - | - | - | $14,000 | |
TOTAL RECOMMENDED | $66,581 | $15,419 |
$42,913
563,175
kWh
|
$6,968
-
Tgal
|
$2,700
-
lb
|
$14,000 | ||
TOTAL IMPLEMENTED | $40,600 | $6,475 |
$37,900
497,763
kWh
|
- |
$2,700
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs