ITAC Assessment: WV0689
ITAC logo
ITAC Assessment: WV0689
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Biomaterials, Medical devices
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $50
M
to 100
M
# of Employees 332
Plant Area 202,250
ft2
Annual Production 100,000
units
Production Hrs. Annual 8,568
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $627,845 12,007,506
kWh
Electricity Demand $239,812 22,731
kW-mo/yr
Electricity Fees $9,837 -
Natural Gas $86,687 54,496
MMBtu
Waste Disposal Costs
Water Usage $96,183 9,110
Tgal
TOTAL YEARLY COSTS $1,060,364
RECOMMENDED SAVINGS* $60,061 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings
01 2.2625: Chill water to the highest temperature possible $23,841 $12,250 $16,066
307,180
kWh
$7,775
-
kW-mo/yr
- - -
02 2.2449: Recover heat from exhausted steam, hot air or hot water $16,980 $75,000 $(-2,096.0)
(-40,076)
kWh
- $1,792
-
MMBtu
$17,284
-
Tgal
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,908 $28,814 $5,711
109,200
kWh
$3,197
-
kW-mo/yr
- - -
04 2.4239: Eliminate or reduce compressed air usage $3,151 $3,917 $2,455
46,945
kWh
$696
-
kW-mo/yr
- - -
05 2.4157: Establish a predictive maintenance program $2,146 $4,200 $2,745
52,487
kWh
$781
-
kW-mo/yr
- - $(-1,380.0)
06 2.4224: Upgrade controls on compressors $1,571 $2,065 $484
9,253
kWh
$1,087
-
kW-mo/yr
- - -
07 2.4221: Install compressor air intakes in coolest locations $962 $4,680 $751
14,369
kWh
$211
-
kW-mo/yr
- - -
08 2.7245: Use direct air supply to exhaust hoods $866 $4,000 $676
12,933
kWh
$190
-
kW-mo/yr
- - -
09 2.1233: Analyze flue gas for proper air/fuel ratio $826 $1,390 - - $826
-
MMBtu
- -
10 2.4239: Eliminate or reduce compressed air usage $576 $700 $449
8,593
kWh
$127
-
kW-mo/yr
- - -
11 2.2511: Insulate bare equipment $234 $786 - - $234
-
MMBtu
- -
TOTAL RECOMMENDED $60,061 $137,802 $27,241
520,884
kWh
$14,064
-
kW-mo/yr
$2,852
-
MMBtu
$17,284
-
Tgal
$(-1,380.0)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs