ITAC Assessment: WV0682
ITAC logo
ITAC Assessment: WV0682
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Feminine wash & cloths, Glycerin suppositories
NAICS 325212: Synthetic Rubber Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $50
M
to 100
M
# of Employees 80
Plant Area 310,000
ft2
Annual Production 5,500,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,020,682 10,853,400
kWh
Electricity Demand $247,494 32,142
kW-mo/yr
Electricity Fees $36,752 -
Natural Gas $140,157 46,564
MMBtu
Waste Disposal Costs
Water Usage $112,337 25,531,267
Tgal
Water Disposal $283,399 25,531,267
Tgal
TOTAL YEARLY COSTS $1,840,821
RECOMMENDED SAVINGS* $281,280 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $98,686 $61,240 $84,495
898,888
kWh
$14,191
-
kW-mo/yr
- - - - -
02 3.4151: Minimize water usage $71,374 $60,060 $(-2,524.0)
(-26,856)
kWh
$(-347.0)
-
kW-mo/yr
- $21,076
-
Tgal
$53,169
-
Tgal
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $18,561 $12,599 $15,558
165,514
kWh
$3,003
-
kW-mo/yr
- - - - -
04 2.4157: Establish a predictive maintenance program $17,883 $6,000 $20,652
219,704
kWh
$2,818
-
kW-mo/yr
- - - $(-5,587.0) -
05 2.2511: Insulate bare equipment $17,044 $488 $16,828
179,023
kWh
$216
-
kW-mo/yr
- - - - -
06 2.7135: Install occupancy sensors $13,054 $14,058 $10,913
116,095
kWh
$2,141
-
kW-mo/yr
- - - - -
07 2.2625: Chill water to the highest temperature possible $7,508 $5,220 $6,723
71,526
kWh
$785
-
kW-mo/yr
- - - - -
08 2.1221: Replace obsolete burners with more efficient ones $7,131 $13,250 - - $7,131
-
MMBtu
- - - -
09 2.1233: Analyze flue gas for proper air/fuel ratio $6,955 $3,160 - - $6,955
-
MMBtu
- - - -
10 2.4151: Develop a repair/replace policy $5,033 $8,967 $4,955
52,711
kWh
$678
-
kW-mo/yr
- - - - $(-600.0)
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,702 $378 $4,140
44,044
kWh
$562
-
kW-mo/yr
- - - - -
12 2.4221: Install compressor air intakes in coolest locations $4,346 $11,060 $3,633
38,645
kWh
$493
-
kW-mo/yr
$220
-
MMBtu
- - - -
13 2.4224: Upgrade controls on compressors $4,273 $13,665 $3,626
38,575
kWh
$647
-
kW-mo/yr
- - - - -
14 2.4239: Eliminate or reduce compressed air usage $3,661 $900 $3,222
34,281
kWh
$439
-
kW-mo/yr
- - - - -
15 2.4239: Eliminate or reduce compressed air usage $1,069 $1,258 $938
9,975
kWh
$131
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $281,280 $212,303 $173,159
1,842,125
kWh
$25,757
-
kW-mo/yr
$14,306
-
MMBtu
$21,076
-
Tgal
$53,169
-
Tgal
$(-5,587.0) $(-600.0)
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs