Assessment Year | 2024 |
---|---|
Principal Product | Hydraulic Cylinders |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $10 M to 50M |
# of Employees | 20 |
Plant Area |
55,000
ft2
|
Annual Production | 3,000
units
|
Production Hrs. Annual | 5,720
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $120,439 | 1,429,200 |
kWh
|
$0.084 | |
Electricity Demand | $42,587 | 4,037 |
kW-mo/yr
|
$10.55 | |
Electricity Fees | $969 | - |
|
- | |
Natural Gas | $1,441 | 101 |
MMBtu
|
$14.27 | |
Waste Disposal Costs | |||||
Water Usage | $1,415 | 149 |
Tgal
|
$9.50 | |
Other Liquid (non-haz) | $30,000 | 19,250 |
gal
|
$1.56 | |
TOTAL YEARLY COSTS | $196,851 | ||||
RECOMMENDED SAVINGS* | $139,410 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $73,416 | $271,368 | - | - | - | - | - | - | $73,416 | |
02 | 3.3131: Use evaporation to concentrate material | $24,278 | $31,216 | - | - | - |
$(-2,749.0)
-
MMBtu
|
$27,027
-
gal
|
- | - | |
03 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $20,948 | $26,406 |
$10,512
124,696
kWh
|
$2,764
-
kW-mo/yr
|
- | - | - | $7,672 | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,264 | $9,760 | - |
$5,264
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,087 | $759 |
$3,237
38,404
kWh
|
$850
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $3,489 | $5,659 |
$2,761
32,748
kWh
|
$728
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4224: Upgrade controls on compressors | $3,058 | $6,936 |
$2,425
28,771
kWh
|
$633
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.4322: Use or replace with energy efficient substitutes | $1,640 | $5,016 |
$1,302
15,444
kWh
|
$338
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,102 | $753 |
$623
7,395
kWh
|
$164
-
kW-mo/yr
|
- |
$315
-
MMBtu
|
- | - | - | |
10 | 2.4239: Eliminate or reduce compressed air usage | $797 | $1,579 |
$628
7,448
kWh
|
$169
-
kW-mo/yr
|
- | - | - | - | - | |
11 | 2.3212: Optimize plant power factor | $596 | $2,964 | - | - | $596 | - | - | - | - | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $401 | $38 |
$317
3,763
kWh
|
$84
-
kW-mo/yr
|
- | - | - | - | - | |
13 | 2.7135: Install occupancy sensors | $334 | $984 |
$207
2,495
kWh
|
$127
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $139,410 | $363,438 |
$22,012
261,164
kWh
|
$11,121
-
kW-mo/yr
|
$596 |
$(-2,434.0)
-
MMBtu
|
$27,027
-
gal
|
$7,672 | $73,416 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs