ITAC Assessment: WV0666
ITAC logo
ITAC Assessment: WV0666
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Industrial Metal Buildings
NAICS 332311: Prefabricated Metal Building and Component Manufacturing
SIC 3448: Prefabricated Metal Buildings and Components
Sales Range $10
M
to 50
M
# of Employees 129
Plant Area 120,000
ft2
Annual Production 430
units
Production Hrs. Annual 2,500
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,235 791,340
kWh
Electricity Demand $33,145 3,132
kW-mo/yr
Electricity Fees $7,727 -
Natural Gas $52,766 4,404
MMBtu
TOTAL YEARLY COSTS $168,873
RECOMMENDED SAVINGS* $18,673 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.7313: Recycle air for heating, ventilation and air conditioning $11,346 $19,500 $1,784
18,756
kWh
$952
-
kW-mo/yr
$9,860
-
MMBtu
$(-1,250.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $5,679 $5,920 $3,669
38,581
kWh
$2,010
-
kW-mo/yr
- -
03 2.4224: Upgrade controls on compressors $859 $3,565 $478
5,022
kWh
$381
-
kW-mo/yr
- -
04 2.4151: Develop a repair/replace policy $445 $1,367 $340
3,578
kWh
$180
-
kW-mo/yr
- $(-75.0)
05 2.6231: Utilize controls to operate equipment only when needed $260 $640 $260
2,730
kWh
- - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $84 $100 $52
552
kWh
$32
-
kW-mo/yr
- -
TOTAL RECOMMENDED $18,673 $31,092 $6,583
69,219
kWh
$3,555
-
kW-mo/yr
$9,860
-
MMBtu
$(-1,325.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs