Assessment Year | 2023 |
---|---|
Principal Product | Skin care, hair color and hair care |
NAICS | 325620: Toilet Preparation Manufacturing |
SIC | 2844: Perfumes, Cosmetics, and Other Toilet Preparations |
Sales Range | $50 M to 100M |
# of Employees | 490 |
Plant Area |
140,000
ft2
|
Annual Production | 20,000
ton
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $448,325 | 5,858,072 |
kWh
|
$0.077 | |
Electricity Demand | $42,998 | 9,862 |
kW-mo/yr
|
$4.36 | |
Electricity Fees | $2,328 | - |
|
- | |
Natural Gas | $88,960 | 20,514 |
MMBtu
|
$4.34 | |
Waste Disposal Costs | |||||
Water Usage | $101,636 | 16,455 |
Tgal
|
$6.18 | |
Water Disposal | $85,731 | 16,455 |
Tgal
|
$5.21 | |
TOTAL YEARLY COSTS | $769,978 | ||||
RECOMMENDED SAVINGS* | $114,417 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $23,719 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,969 | $55,520 |
$25,039
327,310
kWh
|
$2,930
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $23,931 | $31,118 |
$5,235
68,426
kWh
|
$628
-
kW-mo/yr
|
- |
$9,803
-
Tgal
|
$8,265
-
Tgal
|
- | |
03 | 2.1224: Replace boiler | $19,921 | $90,000 | - | - |
$19,921
-
MMBtu
|
- | - | - | |
04 | 2.7241: Install outside air damper / economizer on hvac unit | $14,368 | $70,000 |
$13,583
177,558
kWh
|
$785
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,435 | $1,980 |
$4,890
63,917
kWh
|
$545
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4157: Establish a predictive maintenance program | $5,167 | $1,500 |
$5,713
74,678
kWh
|
$637
-
kW-mo/yr
|
- | - | - | $(-1,183.0) | |
07 | 2.2425: Use flue gases to heat process or service water | $4,509 | $11,550 | - | - |
$4,509
-
MMBtu
|
- | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $3,587 | $3,721 |
$2,180
28,503
kWh
|
$244
-
kW-mo/yr
|
$1,163
-
MMBtu
|
- | - | - | |
09 | 2.4151: Develop a repair/replace policy | $2,563 | $5,683 |
$2,845
37,187
kWh
|
$318
-
kW-mo/yr
|
- | - | - | $(-600.0) | |
10 | 2.4224: Upgrade controls on compressors | $2,313 | $3,080 |
$1,982
25,909
kWh
|
$331
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.7224: Reduce space conditioning during non-working hours | $2,222 | $1,250 | - | - |
$2,222
-
MMBtu
|
- | - | - | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,386 | $200 |
$1,246
16,287
kWh
|
$140
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.1233: Analyze flue gas for proper air/fuel ratio | $807 | $970 | - | - |
$807
-
MMBtu
|
- | - | - | |
14 | 2.2511: Insulate bare equipment | $239 | $503 | - | - |
$239
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $114,417 | $277,075 |
$62,713
819,775
kWh
|
$6,558
-
kW-mo/yr
|
$28,861
-
MMBtu
|
$9,803
-
Tgal
|
$8,265
-
Tgal
|
$(-1,783.0) | ||
TOTAL IMPLEMENTED | $23,719 | $18,887 |
$18,856
246,481
kWh
|
$2,215
-
kW-mo/yr
|
$4,431
-
MMBtu
|
- | - | $(-1,783.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs