| Assessment Year | 2022 |
|---|---|
| Principal Product | Water Treatment |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 4941: Water Supply |
| Sales Range | $1 M to 5M |
| # of Employees | 17 |
| Plant Area |
23,000
ft2
|
| Annual Production | 510,813
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $154,285 | 2,546,957 |
kWh
|
$0.061 |
| Electricity Demand | $43,867 | 4,158 |
kW-mo/yr
|
$10.55 |
| Natural Gas | $1,431 | 248 |
MMBtu
|
$5.77 |
| TOTAL YEARLY COSTS | $199,583 | |||
| RECOMMENDED SAVINGS* | $69,216 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,165 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $30,923 | $89,840 |
$24,973
412,101
kWh
|
$5,950
-
kW-mo/yr
|
- | |
| 02 | 2.5195: Change product design to reduce energy requirements | $22,924 | $32,450 |
$18,514
305,504
kWh
|
$4,410
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,513 | $4,998 |
$9,002
148,543
kWh
|
$2,511
-
kW-mo/yr
|
- | |
| 04 | 2.4224: Upgrade controls on compressors | $2,204 | $1,911 |
$1,708
28,180
kWh
|
$496
-
kW-mo/yr
|
- | |
| 05 | 2.4151: Develop a repair/replace policy | $1,092 | $1,292 |
$939
15,491
kWh
|
$222
-
kW-mo/yr
|
$(-69.0) | |
| 06 | 2.4157: Establish a predictive maintenance program | $560 | $1,500 |
$1,001
16,524
kWh
|
$243
-
kW-mo/yr
|
$(-684.0) | |
| TOTAL RECOMMENDED | $69,216 | $131,991 |
$56,137
926,343
kWh
|
$13,832
-
kW-mo/yr
|
$(-753.0) | ||
| TOTAL IMPLEMENTED | $13,165 | $7,790 |
$10,942
180,558
kWh
|
$2,976
-
kW-mo/yr
|
$(-753.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs