Assessment Year | 2022 |
---|---|
Principal Product | Spark Plugs, Oxygen Sensors |
NAICS | 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing |
SIC | 3694: Electrical Equipment for Internal Combustion Engines |
Sales Range | $50 M to 100M |
# of Employees | 490 |
Plant Area |
309,646
ft2
|
Annual Production | 50,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $455,375 | 9,740,500 |
kWh
|
$0.047 |
Electricity Demand | $298,710 | 14,928 |
kW-mo/yr
|
$20.01 |
Electricity Fees | $1,020 | - |
|
- |
LPG | $21,412 | 837 |
MMBtu
|
$25.58 |
TOTAL YEARLY COSTS | $776,517 | |||
RECOMMENDED SAVINGS* | $82,021 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,574 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $27,447 | $88,959 |
$17,522
374,409
kWh
|
$9,925
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,878 | $1,254 |
$8,714
186,202
kWh
|
$7,164
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $13,895 | $15,573 |
$5,711
122,020
kWh
|
$8,184
-
kW-mo/yr
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,444 | $15,140 |
$7,381
157,720
kWh
|
$6,063
-
kW-mo/yr
|
- | |
05 | 2.6218: Turn off equipment when not in use | $6,486 | $3,744 |
$3,565
76,175
kWh
|
$2,921
-
kW-mo/yr
|
- | |
06 | 2.4151: Develop a repair/replace policy | $2,938 | $1,349 |
$1,661
35,484
kWh
|
$1,361
-
kW-mo/yr
|
$(-84.0) | |
07 | 2.4157: Establish a predictive maintenance program | $1,933 | $1,500 |
$1,771
37,849
kWh
|
$1,461
-
kW-mo/yr
|
$(-1,299.0) | |
TOTAL RECOMMENDED | $82,021 | $127,519 |
$46,325
989,859
kWh
|
$37,079
-
kW-mo/yr
|
$(-1,383.0) | ||
TOTAL IMPLEMENTED | $54,574 | $38,560 |
$28,803
615,450
kWh
|
$27,154
-
kW-mo/yr
|
$(-1,383.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs