ITAC Assessment: WV0624
ITAC logo
ITAC Assessment: WV0624
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Modular Carpet
NAICS 314110: Carpet and Rug Mills
SIC 2273: Carpets and Rugs
Sales Range $50
M
to 100
M
# of Employees 490
Plant Area 1,932,820
ft2
Annual Production 20,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $702,788 30,331,475
kWh
Electricity Demand $1,177,248 57,429
kW-mo/yr
Electricity Fees $4,105 -
Natural Gas $694,639 151,668
MMBtu
Waste Disposal Costs
Solid Waste (non-haz) $212,826 6,921,160
lb
TOTAL YEARLY COSTS $2,791,606
RECOMMENDED SAVINGS* $509,285 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $102,551

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.3412: Use waste heat to produce steam to drive a steam turbine-generator $194,747 $906,700 $18,920
819,060
kWh
$23,001
-
kW-mo/yr
- $212,826
-
lb
$(-60,000.0)
02 2.2437: Recover waste heat from equipment $59,403 $137,330 - - $59,403
-
MMBtu
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $46,923 $170,200 $21,175
916,647
kWh
$25,748
-
kW-mo/yr
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $46,261 $53,185 $15,306
662,578
kWh
$30,955
-
kW-mo/yr
- - -
05 2.4224: Upgrade controls on compressors $39,601 $115,224 $15,985
691,987
kWh
$23,616
-
kW-mo/yr
- - -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $33,682 $7,000 - $33,682
-
kW-mo/yr
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $26,225 $2,763 $11,834
512,276
kWh
$14,391
-
kW-mo/yr
- - -
08 2.4239: Eliminate or reduce compressed air usage $16,511 $450 $7,450
322,498
kWh
$9,061
-
kW-mo/yr
- - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,209 $15,750 $3,382
146,427
kWh
$6,827
-
kW-mo/yr
- - -
10 2.4151: Develop a repair/replace policy $6,918 $2,242 $3,300
142,836
kWh
$4,018
-
kW-mo/yr
- - $(-400.0)
11 2.4157: Establish a predictive maintenance program $6,371 $1,500 $3,519
152,359
kWh
$4,285
-
kW-mo/yr
- - $(-1,433.0)
12 2.2449: Recover heat from exhausted steam, hot air or hot water $5,615 $6,090 - - $5,615
-
MMBtu
- -
13 2.1233: Analyze flue gas for proper air/fuel ratio $5,157 $6,050 - - $5,157
-
MMBtu
- -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $4,241 $6,840 $1,781
77,095
kWh
$2,460
-
kW-mo/yr
- - -
15 2.2425: Use flue gases to heat process or service water $3,975 $11,340 - - $3,975
-
MMBtu
- -
16 2.2511: Insulate bare equipment $3,078 $3,446 - - $3,078
-
MMBtu
- -
17 2.4239: Eliminate or reduce compressed air usage $368 $725 $163
7,062
kWh
$205
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $509,285 $1,446,835 $102,815
4,450,825
kWh
$178,249
-
kW-mo/yr
$77,228
-
MMBtu
$212,826
-
lb
$(-61,833.0)
TOTAL IMPLEMENTED $102,551 $31,016 $28,047
1,214,126
kWh
$68,102
-
kW-mo/yr
$8,235
-
MMBtu
- $(-1,833.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs