| Assessment Year | 2022 |
|---|---|
| Principal Product | Metal Stamped Parts |
| NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
| SIC | 3469: Metal Stampings, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 54 |
| Plant Area |
65,079
ft2
|
| Annual Production | 28,000,000
pieces
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $102,567 | 1,396,438 |
kWh
|
$0.073 |
| Electricity Demand | $72,460 | 6,868 |
kW-mo/yr
|
$10.55 |
| TOTAL YEARLY COSTS | $175,027 | |||
| RECOMMENDED SAVINGS* | $24,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,898 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $10,582 | $19,059 |
$6,816
92,857
kWh
|
$3,766
-
kW-mo/yr
|
- | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,162 | $5,562 |
$3,326
45,317
kWh
|
$1,836
-
kW-mo/yr
|
- | - | |
| 03 | 2.4224: Upgrade controls on compressors | $2,975 | $13,590 |
$2,099
28,590
kWh
|
$876
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,562 | $209 |
$1,003
13,667
kWh
|
$559
-
kW-mo/yr
|
- | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $973 | $655 |
$625
8,515
kWh
|
$348
-
kW-mo/yr
|
- | - | |
| 06 | 2.3212: Optimize plant power factor | $811 | $2,732 | - | - | $811 | - | |
| 07 | 2.4221: Install compressor air intakes in coolest locations | $743 | $2,460 |
$480
6,539
kWh
|
$263
-
kW-mo/yr
|
- | - | |
| 08 | 2.4151: Develop a repair/replace policy | $648 | $2,086 |
$515
7,021
kWh
|
$285
-
kW-mo/yr
|
- | $(-152.0) | |
| 09 | 2.4157: Establish a predictive maintenance program | $454 | $1,000 |
$1,099
14,977
kWh
|
$612
-
kW-mo/yr
|
- | $(-1,257.0) | |
| 10 | 2.4239: Eliminate or reduce compressed air usage | $450 | $638 |
$292
3,972
kWh
|
$158
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $24,360 | $47,991 |
$16,255
221,455
kWh
|
$8,703
-
kW-mo/yr
|
$811 | $(-1,409.0) | ||
| TOTAL IMPLEMENTED | $4,898 | $7,320 |
$3,534
48,152
kWh
|
$1,962
-
kW-mo/yr
|
$811 | $(-1,409.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs