ITAC Assessment: WV0612
ITAC logo
ITAC Assessment: WV0612
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Glassware
NAICS 327212: Other Pressed and Blown Glass and Glassware Manufacturing
SIC 3229: Pressed and Blown Glass and Glassware, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 8
Plant Area 65,054
ft2
Annual Production 80,000
units
Production Hrs. Annual 2,210
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $20,231 328,960
kWh
Electricity Demand $9,622 910
kW-mo/yr
Electricity Fees $184 -
Natural Gas $330,797 59,000
MMBtu
TOTAL YEARLY COSTS $360,834
RECOMMENDED SAVINGS* $97,798 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,407

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.1125: Convert to oxyfuel burners $30,507 $81,760 $5,941
96,604
kWh
- $81,839
-
MMBtu
- $(-57,273.0)
02 2.2425: Use flue gases to heat process or service water $22,389 $99,385 $(-2,329.0)
(-37,878)
kWh
- $24,718
-
MMBtu
- -
03 2.1233: Analyze flue gas for proper air/fuel ratio $15,446 $16,700 - - $16,106
-
MMBtu
$(-660.0) -
04 2.1122: Re-size charging openings or add a movable door on equipment $13,924 $27,550 - - $13,924
-
MMBtu
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,798 $7,637 $3,149
51,207
kWh
$1,649
-
kW-mo/yr
- - -
06 2.7447: Install vinyl strip / high speed / air curtain doors $3,641 $4,320 $(-684.0)
(-11,130)
kWh
- $4,325
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,008 $8,132 $1,496
24,327
kWh
$1,512
-
kW-mo/yr
- - -
08 2.1221: Replace obsolete burners with more efficient ones $1,683 $8,044 - - $1,683
-
MMBtu
- -
09 2.1321: Replace fossil fuel equipment with electrical equipment $1,090 $1,341 $(-1,484.0)
(-24,135)
kWh
$(-349.0)
-
kW-mo/yr
$2,923
-
MMBtu
- -
10 2.6241: Reduce temperature of process equipment when on standby $701 $397 - - $701
-
MMBtu
- -
11 2.6232: Install set-back timers $611 $1,110 $378
6,153
kWh
$233
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $97,798 $256,376 $6,467
105,148
kWh
$3,045
-
kW-mo/yr
$146,219
-
MMBtu
$(-660.0) $(-57,273.0)
TOTAL IMPLEMENTED $23,407 $30,659 $1,190
19,350
kWh
$1,745
-
kW-mo/yr
$21,132
-
MMBtu
$(-660.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs