Assessment Year | 2019 |
---|---|
Principal Product | Wood Products |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 67 |
Plant Area |
250,000
ft2
|
Annual Production | 15,000
thousand feet
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $279,928 | 4,143,686 |
kWh
|
$0.068 |
Electricity Demand | $132,372 | 13,587 |
kW-mo/yr
|
$9.74 |
Electricity Fees | $8,974 | - |
|
- |
Natural Gas | $15,826 | 1,835 |
MMBtu
|
$8.62 |
Wood | $360,000 | 192,000 |
MMBtu
|
$1.88 |
TOTAL YEARLY COSTS | $797,100 | |||
RECOMMENDED SAVINGS* | $84,833 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $63,510 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4157: Establish a predictive maintenance program | $21,112 | $1,000 |
$13,695
202,592
kWh
|
$9,467
-
kW-mo/yr
|
- | $(-2,050.0) | |
02 | 2.7135: Install occupancy sensors | $17,040 | $19,272 |
$10,066
148,907
kWh
|
$6,974
-
kW-mo/yr
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $15,334 | $3,500 | - | - |
$15,484
-
MMBtu
|
$(-150.0) | |
04 | 2.1221: Replace obsolete burners with more efficient ones | $11,713 | $2,200 | - | - |
$11,713
-
MMBtu
|
- | |
05 | 2.4224: Upgrade controls on compressors | $5,475 | $8,000 |
$5,475
80,998
kWh
|
- | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,044 | - |
$2,993
44,291
kWh
|
$2,051
-
kW-mo/yr
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,135 | $4,150 |
$4,135
61,169
kWh
|
- | - | - | |
08 | 2.4151: Develop a repair/replace policy | $3,383 | $763 |
$2,234
33,041
kWh
|
$1,549
-
kW-mo/yr
|
- | $(-400.0) | |
09 | 2.2511: Insulate bare equipment | $1,597 | $8,060 | - | - |
$1,597
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $84,833 | $46,945 |
$38,598
570,998
kWh
|
$20,041
-
kW-mo/yr
|
$28,794
-
MMBtu
|
$(-2,600.0) | ||
TOTAL IMPLEMENTED | $63,510 | $32,595 |
$28,988
428,831
kWh
|
$20,041
-
kW-mo/yr
|
$17,081
-
MMBtu
|
$(-2,600.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs