ITAC Assessment: CO0480
ITAC logo
ITAC Assessment: CO0480
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product greeting cards
NAICS
n/a
SIC 2771: Greeting Cards
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 160,000
ft2
Annual Production 50,000,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,405 2,194,696
kWh
Electricity Demand $93,078 6,732
kW-mo/yr
Electricity Fees $1,076 -
Natural Gas $19,413 4,034
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,300 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,650

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.3191: Use demand controller or load shedder $4,830 $8,000 - $4,830
-
kW-mo/yr
- -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,250 $12,950 $2,250
137,400
kWh
- - -
03 2.7221: Lower temperature during the winter season and vice-versa $1,810 $1,470 - - $1,810
-
MMBtu
-
04 2.7224: Reduce space conditioning during non-working hours $1,810 $3,750 - - $1,810
-
MMBtu
-
05 2.2211: Use optimum temperature $610 $200 $130
7,800
kWh
$480
-
kW-mo/yr
- -
06 2.2211: Use optimum temperature $500 - $100
5,900
kWh
$400
-
kW-mo/yr
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $460 $60 $140
8,700
kWh
$320
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $30 - $40
2,300
kWh
$140
-
kW-mo/yr
- $(-150.0)
TOTAL RECOMMENDED $12,300 $26,430 $2,660
162,100
kWh
$6,170
-
kW-mo/yr
$3,620
-
MMBtu
$(-150.0)
TOTAL IMPLEMENTED $3,650 $5,220 $40
2,300
kWh
$140
-
kW-mo/yr
$3,620
-
MMBtu
$(-150.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs